  • Question 51:

    You manage a project according to the schedule as shown in the exhibit. (Click the Exhibit button.)

    You need to set the Task Mode for task 4 to be the same as task 6. What should you do?

    A. Create a task dependency from Task 4 to Task 6.
    B. Set Task 4 as critical.
    C. Add a 1 day lead to Task 4.
    D. Set Task 4 as manually scheduled.

  • Question 52:

    You track all costs on your project. You need to track task-level airfare costs that do not depend on the amount of work or duration of a task. What should you do?

    A. Use a work type resource.
    B. Create a custom field and capture travel costs at the project level.
    C. Use a budget resource.
    D. Use a cost type resource.

  • Question 53:

    You manage several projects saved on a shared drive.

    You want to create a critical path relationship between several schedules managed by other project managers.

    You need to link the project schedules at the task level. You also need to ensure that each project manager can continue to manage their own project.

    What should you do?

    A. ?Open each individual project.?Create date constraints for task deadlines.?Save the project.
    B. ?Open a blank project.?Insert each project and select the Link to project option.?Link tasks as needed.?Save the subprojects.
    C. ?Open a blank project.?Copy and paste each project into the new file.?Link tasks as needed.?Save the project by using a new name.
    D. ?Open a blank project.?Insert each project and select the Link to project option.?Save the blank project as a new named project.?Discard the subprojects.
    E. ?Open a blank project.?Insert each project and clear the Link to project option.?Save the blank project as a new named project.?Discard the subprojects.

  • Question 54:

    Your project has some resources with rates that adjust over time.

    You need to ensure that project costs automatically adjust for these resources.

    What should you do?

    A. Create cost tables to include rates that activate on effective dates.
    B. Change the resource availability settings to establish Units for selected dates.
    C. Create resources that include fixed Standard costs, and then apply a rate variance per project task.
    D. Create a named resource for each Standard hourly rate.

  • Question 55:

    You have a task named Tasks that has a duration of four days and a finish-to-finish relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You also need to retain the original duration and resource assignments. You select Tasks. What should you do next?

    A. Remove the predecessor assignments.
    B. Click the Insert Milestone button.
    C. Select the Mark Task as Milestone check box.
    D. Change Work to zero hours.

  • Question 56:

    You need to select a view that allows you to use the drag-and-drop feature on the resource assignments and unassigned tasks. What should you do?

    A. Select the Gantt Chart view, split the window, and then select the Resource Usage view for the details pane.
    B. Select the Team Planner view.
    C. Select the Timeline view.
    D. Select the Gantt Chart view, and then click Assign Resources.

  • Question 57:

    You have team members who work on one of the following shifts: Monday through Friday: 8 hours a day. Tuesday through Saturday: 10 hours a day. Sunday through Wednesday: 12 hours a day. You need to ensure that your project plan accommodates the different shifts.

    What should you do?

    A. Create shift resource departments.
    B. Change the maximum units for each resource.
    C. Create three tasks, one for each shift.
    D. Create a base calendar for each shift.

  • Question 58:

    You use Project Professional 2010 to manage a software development project as shown in the exhibit. (Click the Exhibit button.)

    You need to cancel the Develop prototype based on functional specifications task. You also need to retain all the information from the task.

    Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

    A. Delete the task.
    B. Set the tasks remaining work to 0 hours.
    C. Inactivate the task.
    D. Make the task 100 percent complete.
    E. Create a link from the Develop functional specifications task to the Review functional specifications task.

  • Question 59:

    You need to view only the task name, start and finish dates, percentage of work completed, and a Gantt chart. What should you do?

    A. Create a custom filter and a custom view.
    B. Create a custom table and a custom group.
    C. Create a custom filter and a custom table.
    D. Create a custom table and a custom view.

  • Question 60:

    Your project has Subject Matter Experts (SMEs) who are consulted for each task.

    You need to create a single field that includes a list of SME names that can be associated with each task.

    What should you do?

    A. Create a task custom field that includes a lookup table custom attribute.
    B. Enter the list of SME names on the Resource tab of the Task Information window.
    C. Create a project custom field that includes a lookup table custom attribute.
    D. Create a resource custom field that includes a lookup table custom attribute.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 70-178 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.