70-178 Exam Details

  • Exam Code
    :70-178
  • Exam Name
    :Microsoft Project 2010, Managing Projects
  • Certification
    :Microsoft Certifications
  • Vendor
    :Microsoft
  • Total Questions
    :65 Q&As
  • Last Updated
    :Dec 07, 2021

Microsoft 70-178 Online Questions & Answers

  • Question 41:

    The project you manage has only part-time resources.

    The part-time resources work four hours a day from Wednesday through Saturday.

    You need to create a new calendar and set the calendar as the default for your project.

    Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

    A. Select the part-time calendar from the Change Working Time window.
    B. Set the calendar type to part-time for all tasks.
    C. Select the part-time calendar from the Project Information window.
    D. On the Project tab, Select Change Working Time, and then click Create New Calendar.
    E. Change the Calendar type in the Project Options dialog box.

  • Question 42:

    You receive approval for a project plan that is yet to start.

    You need to ensure that all project tasks start no earlier than September 13, 2010.

    Which project level field should you set?

    A. Change the Status Date field to 9/13/2010.
    B. In the Current Date field, type 9/13/2010.
    C. In the Start Date field, type 9/13/2010.
    D. Change the calendar type in the Project Options dialog box.

  • Question 43:

    You create a new Gantt Chart view. You need to copy the view to a different project. What should you do?

    A. Use the Links Between Projects tool.
    B. Use the Organizer tool.
    C. Use the Save Views feature.
    D. Use the Compare Projects feature.

  • Question 44:

    You update your project schedule based on information received from your team members in today's status meeting. You need to compare the current revised project schedule with the baseline schedule side by side. Which default view should you use?

    A. Calendar
    B. Multiple Baselines Gantt
    C. Leveling Gantt
    D. Tracking Gantt
    E. Timeline

  • Question 45:

    A section of your project contains only a summary task along with four subtasks and a milestone.

    You discover that the section is located in the incorrect phase and has the incorrect Work Breakdown Structure (WBS) numbering.

    You need to move the section to another phase of the project. You also need to ensure that the section reflects the correct WBS numbering.

    What should you do?

    A. Select the summary task and change the scheduling mode to Manually Scheduled.
    B. Select the entire section and click Move Task.
    C. Drag the summary task.
    D. Modify the start and finish dates of the summary task.

  • Question 46:

    Every time you create a new task within your project schedule, Project 2010 automatically adds a dependency to the new task.

    You need to turn off the feature that triggers the dependency to be automatically added.

    What should you do?

    A. On the Advanced tab of the Project 2010 options, clear the Move selection after enter check box.
    B. On the Schedule tab of the Project 2010 options, clear the Autolink inserted or moved tasks check box.
    C. On the Advanced tab of the Project 2010 options, select the Ask to update automatic links check box.
    D. Highlight all tasks and select Respect Links.

  • Question 47:

    You have a Project 2010 schedule that contains the following tasks:

    1.

    Inactive tasks

    2.

    Manually scheduled tasks

    3.

    Manually scheduled summary tasks

    4.

    Tasks that contain strikethrough font

    You want to save the schedule as a Project 2007 project.

    You need to ensure that no new milestones are created.

    What should you do?

    A. Change all inactive tasks to active tasks.
    B. Change all tasks that contain strikethrough font to tasks that include normal font.
    C. Change all manually scheduled summary tasks to automatic scheduling.
    D. Change all manually scheduled tasks to automatic scheduling.

  • Question 48:

    The dates of your project are displayed in the long date format as Wed 09-01-28 12:33.

    You need to ensure that the dates are displayed as 1/28/09.

    What should you do?

    A. On the Format menu, modify the settings in the Layout dialog box.
    B. On the File menu, modify the settings in the Options dialog box.
    C. On the Format menu, modify the settings in the Text Styles dialog box.
    D. Modify the settings in the Field Settings dialog box.

  • Question 49:

    You have a list of tasks in Microsoft Excel 2010.

    You need to create a Microsoft Project 2010 schedule that maintains the order of the tasks.

    Which two actions could you perform? (Each correct answer presents a complete solution. Choose two.)

    A. From Excel 2010, save the file by using the .mpp file extension.
    B. From Project 2010, use the New from Excel workbook wizard.
    C. From Project 2010, use the Open command and select the Excel file.
    D. From Excel 2010, save the file by using the .mpt file extension.

  • Question 50:

    Your project contains many tasks that have dependencies and result in independent networks of tasks. You need to ensure that you can view critical tasks on all independent networks of tasks within the project. What should you do?

    A. View the project's Gantt chart and apply the Critical filter.
    B. On the Advanced tab of the Microsoft Project 2010 options, select the Calculate multiple critical paths check box.
    C. View the project's Gantt chart and apply the Critical group.
    D. On the Advanced tab of the Microsoft Project 2010 options, modify the Tasks are critical if slack is less than or equal to option.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 70-178 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.