You manage several projects. Each project has shared resources and work distribution.
You need to ensure that you can adjust the workload for specific resources used across multiple project schedules.
What should you do?
A. Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on each project.Five resources work full time on the project. Standard working hours are eight hours a day from Monday through Friday.
John, a team member, asks to take Thursday off from work. He will work on Saturday to adjust this time.
You need to ensure that the change in John's working time is reflected in the project schedule.
What should you do?
A. Update the resource calendar for John by making Thursday as a non-working day and Saturday as a working day.You need to view Task ID 0 on your project plan. What should you do?
A. On the Advanced tab of the Project 2010 options, select Show Status Bar.Your project contains several baselines. By mistake, you save one of your baselines in Baseline5.
You need to move Baseline5 to Baseline3 while preserving the baseline information. You also need to create a new Baseline5 by using today's data.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A. From the Clear Baseline window, click Clear baseline plan and select Baseline3.You want to print the Gantt Chart view of your project.
You need to hide the Gantt chart legend.
What should you do?
A. Edit the view.You need to create a project plan that accommodates the corporate holiday calendar. What should you do?
A. Add exceptions to the project calendar for corporate holidays.You create several new tasks by using the Manually Scheduled Task option.
You need to automatically calculate the start and finish dates for linked manually scheduled tasks.
You need to achieve this goal while retaining manually scheduled tasks within the project.
What should you do?
A. Modify the values of Scheduled Start and Scheduled Finish.Your customer wants to receive your project's Timeline view in a document by e-mail.
You need to create a document that contains only the Timeline view.
You select the Timeline view. What should you do next?
A. Select Sync With Task List.You need to replace the resource assignment for an in-progress task.
You also need to retain the Work, Actual Work, Remaining Work, and Baseline data for the task.
What should you do?
A. Use the Resource Name column drop-down list.You need to ensure that when you add new tasks, the project schedule doesn't set a start date and end date. What should you do?
A. Select Task from the main ribbon menu. Highlight the task that you want to change and select Manually Schedule.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 70-178 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.