The milestones in your project schedule represent the end of phases.
You need to change the background color of the cells of the milestones to blue. What should you do on the Format tab?
A. Select Text Styles, and then select Milestone Tasks.You need to ensure that you can view only the tasks on your projects critical path. What should you do?
A. On the Advanced tab of the Project 2010 options, select the Calculate multiple critical paths check box.You create a custom Timeline view of summary tasks and key milestones.
You need to send an image of only the custom Timeline view by e-mail.
Which two actions could you perform? (Each correct answer presents a complete solution. Choose two.)
A. On the File menu, select Save and Send, and then click Create a PDF/XPS Document.You need to compare the total work of your project's deliverables against the baseline work. What should you do?
A. From the Gantt Chart view, change the table to display the Work table.You have added two new tasks to your project. Both tasks are subtasks to a summary task. You need to update Baseline1 only for the two new tasks. What should you do?
A. Highlight the two tasks. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, select To all summary tasks, and then click OK.You need to create a new project schedule by using tasks from an existing project. You need to achieve this goal without inheriting actual hours from the existing project. What would you do first?
A. On the File menu in Project 2010, use one of the existing templates.Your project schedule contains both Work and Material resources. The resources are assigned to tasks and are of either the committed or proposed booking type.
You need to ensure that the project does not contain over-allocated resources.
Which feature should you use?
A. Clear LevelingYou need to import a task list from a Microsoft Office SharePoint 2010 site to create a project schedule in Project 2010.
You need to achieve this goal while maintaining SharePoint synchronization.
What should you do?
A. Use the Save to SharePoint feature and type the URL that contains the task list.You have two dependent tasks named Task 1 and Task 2. Task 1 is the predecessor for Task 2. You need to ensure that when the duration of Task 1 changes, the scheduled start date for Task 2 does not change automatically. How should you configure Task 2?
A. Set the task type to Fixed Duration.In the default Gantt Chart view of your Project Professional 2010 project, you need to display the following information:
Tasks that are not started.
Tasks in progress.
Tasks that have finished.
Total remaining effort for each group of tasks.
What should you do on the View tab?
A. Select Group by Complete and Incomplete Tasks, and then add the Remaining Work field to the table.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 70-178 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.