70-178 Exam Details

  • Exam Code
    :70-178
  • Exam Name
    :Microsoft Project 2010, Managing Projects
  • Certification
    :Microsoft Certifications
  • Vendor
    :Microsoft
  • Total Questions
    :65 Q&As
  • Last Updated
    :Dec 07, 2021

Microsoft 70-178 Online Questions & Answers

  • Question 1:

    The milestones in your project schedule represent the end of phases.

    You need to change the background color of the cells of the milestones to blue. What should you do on the Format tab?

    A. Select Text Styles, and then select Milestone Tasks.
    B. Select Layout, and then select Show drawings.
    C. Select Drawing, and then select Text Box.
    D. Select Column Settings, and then select Milestone.
    E. Select Bar Styles, and then select Milestone.

  • Question 2:

    You need to ensure that you can view only the tasks on your projects critical path. What should you do?

    A. On the Advanced tab of the Project 2010 options, select the Calculate multiple critical paths check box.
    B. View the projects Gantt chart and apply the Critical group.
    C. View the project's Gantt chart and apply the Critical filter.
    D. On the Advanced tab of the Project 2010 options, modify the Tasks are critical if slack is less than or equal to option.

  • Question 3:

    You create a custom Timeline view of summary tasks and key milestones.

    You need to send an image of only the custom Timeline view by e-mail.

    Which two actions could you perform? (Each correct answer presents a complete solution. Choose two.)

    A. On the File menu, select Save and Send, and then click Create a PDF/XPS Document.
    B. On the File menu, select Save and Send, and then click Send as Attachment.
    C. On the Format tab, select Copy Timeline, and then click For email.
    D. Copy and paste the Timeline view into the body of the e-mail.

  • Question 4:

    You need to compare the total work of your project's deliverables against the baseline work. What should you do?

    A. From the Gantt Chart view, change the table to display the Work table.
    B. Use the Task Usage view and the Task Form in the details pane.
    C. From the Task Sheet view, change the table to display the Summary table.
    D. Use the Tracking Gantt view and display the default Entry table.

  • Question 5:

    You have added two new tasks to your project. Both tasks are subtasks to a summary task. You need to update Baseline1 only for the two new tasks. What should you do?

    A. Highlight the two tasks. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, select To all summary tasks, and then click OK.
    B. Highlight the summary task. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, select To all summary tasks, and then click OK.
    C. Highlight the summary task. Click Set Baseline and select Baseline1.Click the Entire Project radio button, and then click OK.
    D. Highlight the two tasks. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, and then click OK.

  • Question 6:

    You need to create a new project schedule by using tasks from an existing project. You need to achieve this goal without inheriting actual hours from the existing project. What would you do first?

    A. On the File menu in Project 2010, use one of the existing templates.
    B. Save the task list in Microsoft Excel and use the Project Import Wizard.
    C. Open the previously saved project schedule and save it as a template.
    D. Save the task list as a Microsoft Excel template.

  • Question 7:

    Your project schedule contains both Work and Material resources. The resources are assigned to tasks and are of either the committed or proposed booking type.

    You need to ensure that the project does not contain over-allocated resources.

    Which feature should you use?

    A. Clear Leveling
    B. Assign Resources
    C. Resource Pool C Share Resources
    D. Level All

  • Question 8:

    You need to import a task list from a Microsoft Office SharePoint 2010 site to create a project schedule in Project 2010.

    You need to achieve this goal while maintaining SharePoint synchronization.

    What should you do?

    A. Use the Save to SharePoint feature and type the URL that contains the task list.
    B. Open the SharePoint task list in Datasheet view and copy the tasks to a blank project file.
    C. Use the New from SharePoint feature and type the URL that contains the task list.
    D. Save the SharePoint task list to a Microsoft Excel file and use the Project Import Wizard.

  • Question 9:

    You have two dependent tasks named Task 1 and Task 2. Task 1 is the predecessor for Task 2. You need to ensure that when the duration of Task 1 changes, the scheduled start date for Task 2 does not change automatically. How should you configure Task 2?

    A. Set the task type to Fixed Duration.
    B. Set the lag to two elapsed days (2ed).
    C. Set the constraint type to Start No Earlier Than.
    D. Set the schedule mode to Manually Scheduled.

  • Question 10:

    In the default Gantt Chart view of your Project Professional 2010 project, you need to display the following information:

    Tasks that are not started.

    Tasks in progress.

    Tasks that have finished.

    Total remaining effort for each group of tasks.

    What should you do on the View tab?

    A. Select Group by Complete and Incomplete Tasks, and then add the Remaining Work field to the table.
    B. Select Group by Complete and Incomplete Tasks, and then add the Work field to the table.
    C. Select Group by Active v. Inactive, and then add the Remaining Work field to the table.
    D. Select Group by Active v. Inactive, and then add the Work field to the table.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 70-178 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.