  • Question 21:

    Your project has a part-time resource who works 4 hours a day from Monday through Thursday.

    You need to ensure that your project plan accommodates the part-time resource.

    What should you do?

    A. Update the base project calendar.
    B. Change the working time for the resource.
    C. Change the maximum units for the resource.
    D. Assign the resource only to tasks that are scheduled on the working days.

  • Question 22:

    All tasks in your project use the Auto Schedule mode.

    Several tasks are in progress.

    You need to reschedule all the remaining work on the project. You also need to achieve this goal without having rigid constraints set to your project's tasks.

    What should you do?

    A. Click Update Project.
    B. Click Calculate Project.
    C. Change the Status Date field.
    D. Click Move Project.

  • Question 23:

    The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do?

    A. Select the Project Summary Task option.
    B. Select the Summary Tasks option.
    C. Create a manually scheduled summary task.
    D. Update the project calendar.

  • Question 24:

    One of your tasks in your project plan is 50 percent complete. The task has a finish variance of 4 days and a work variance of -14 days. Which set of values describes the task?

    A. The task is early by 14 days.
    B. The task is early by 4 days.
    C. The task is late by 4 days.
    D. The task is late by 14 days.

  • Question 25:

    You manage a project that specifies all constraint types to As Soon As Possible.

    You discover that one of your key tasks is scheduled to end prior to the targeted finish date.

    You need to display the targeted finish date on the default Gantt chart.

    What should you modify in the Task Information window?

    A. Set the Deadline date field.
    B. Set the Constraint date field.
    C. Set the Finish date field.
    D. Select the Mark task as milestone check box.
    E. Select the Display on Timeline check box.

  • Question 26:

    Standard working hours are eight hours a day from Monday through Friday. You create a task of fixed units and set the duration to 2 days.

    You assign the task to John at 100 percent. John wants to work only 50 percent on the task. You change John's assignment units to 50 percent for the task.

    Which set of values describes the specified task?

    A. Duration shows 2 days; Work shows 0 hours
    B. Duration shows 4 days; Work shows 16 hours
    C. Duration shows 4 days; Work shows 8 hours
    D. Duration shows 2 days; Work shows 8 hours
    E. Duration shows 2 days; Work shows 16 hours

  • Question 27:

    You need to create a project plan in Project 2010 from a list of tasks in a Microsoft Access 2010 database. What should you do?

    A. From Windows Explorer, change the file extension of the Access 2010 file to .mpp, and then open the file in Project 2010.
    B. From Project 2010, use the ODBC feature.
    C. Use the Project Import Wizard.
    D. In the Visual Reports dialog box, click the Save Data button and use the Field Picker option.

  • Question 28:

    You need to view the following information for your project: Which component will display the information?

    A. Thedefault Resource Sheet
    B. Thedefault Task Sheet
    C. TheProject Statistics window
    D. Thedefault Cost Table

  • Question 29:

    The red person icon is displayed next to one of your tasks. You need to find out the reason for the display of the icon. What should you do?

    A. Display the task details.
    B. Use the Level Resource feature.
    C. Use the Task Inspector tool.
    D. View the task information.

  • Question 30:

    You need to be able to send the custom Quick Access Toolbar to all users. What should you do?

    A. Use the Reset all customizations option.
    B. Use the Organizer tool.
    C. Save the project as a Project 2010 template (.mpt) file.
    D. Use the Export all customizations option.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 70-178 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.