PRINCE2 PRINCE2-FOUNDATION Online Questions & Answers

  • Question 851:

    Which PRINCE2 role has a specific responsibility for briefing non-technical management on supplier aspects of the project?

    A. Team Manager
    B. Project Manager
    C. Senior Supplier
    D. Team member

  • Question 852:

    Which is a recommended quality review team role?

    A. Project Manager
    B. Assurance
    C. Project Support
    D. Administrator

  • Question 853:

    Which product contains the customer's quality expectations?

    A. Quality Register
    B. Quality Management Strategy
    C. Project Product Description
    D. Business Case

  • Question 854:

    Which are the specific roles of the PRINCE2 quality review technique?

    A. Presenter, Chair, Reviewer, Administrator
    B. Chair, Project Manager, Project Support, User
    C. Reviewer, Administrator, Project Assurance, Executive
    D. Stakeholder, Team Manager, Project Support, Reviewer

  • Question 855:

    Once a product has been completed, from whom would the Team Manager get approval for its completion?

    A. Project Manager
    B. The authority defined in the product's Product Description
    C. Quality Assurance as part of their independent audits
    D. The producer of the product

  • Question 856:

    What is a purpose of the Change theme?

    A. Prevent change to anything agreed in the Project Initiation Documentation
    B. Ensure any potential changes to baselined products are controlled
    C. Ensure that the correct versions are delivered to the customer
    D. Assess changes to only the specialist products

  • Question 857:

    What role is responsible for creating a Team Plan in the Managing Product Delivery process?

    A. Project Manager
    B. Team Manager
    C. Project Support
    D. Senior User

  • Question 858:

    How should the Team Manager report that tolerances are forecast to be exceeded?

    A. Create an Exception Report
    B. Create a Highlight Report
    C. Raise an issue
    D. Grant a concession

  • Question 859:

    According to PRINCE2, which characteristic is necessary for an effective project board?

    A. An ability to delegate
    B. An attention to detail
    C. A calm management style
    D. A 'problem-solving' approach

  • Question 860:

    When is the Communication Management Strategy created?

    A. When designing and appointing the project management team
    B. During the initiation stage
    C. When producing a more detailed stage plan for the next stage of the project
    D. As soon as the Project Board have authorized the project

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.