Which PRINCE2 theme has a purpose to facilitate communication and control by defining the means of delivering the products?
A. Plans
B. Progress
C. Organization
D. Change
Identify the missing word(s) in the following sentence... The development and maintenance of a credible [?] provides a baseline against which progress can be measured.
A. Product
B. Product Status Account
C. Business Case
D. Plan
Which of the following would define the sequence in which the products are to be created and any dependencies between them?
A. Product Status Account
B. Product flow diagram
C. Product breakdown structure
D. Product Description
According to PRINCE2, Project Board members would NOT be involved in which of the following?
A. Confirming project tolerances with corporate or programme management
B. Authorizing the start of the project
C. Running of the project on a day-to-day basis
D. Communications between the project management team and stakeholders external to that team
Which product is the Executive specifically responsible for overseeing the development of?
A. Project mandate
B. Work Package
C. Outline Business Case
D. Project approach
Which of the following does PRINCE2 say are typical characteristics of a Project Board member?
A. Democratic, supportive, can make decisions
B. Hard working, experienced, forceful
C. Focused, steadfast, autocratic
D. Have authority, credibility, ability to delegate, available when required
Who is responsible for providing the project mandate?
A. Project Support
B. Corporate or programme management
C. Project Manager
D. Project Board
Who determines the use of a change authority and change budget during project initiation?
A. Project Board
B. Senior User
C. Project Manager
D. Corporate or Programme Management
Which role is the key decision-maker on the project management team and is ultimately accountable for the project's success?
A. Corporate or programme management
B. Change Authority
C. Project Manager
D. Executive
If the Project Board wish to ensure the Communications Management Strategy covers all the stakeholders requirements for the next stage, which project management team role may they appoint to check this for them?
A. Project Assurance
B. Project Support
C. Project Manager
D. Quality Assurance
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.