Which is a minimum requirement for applying the quality theme?
A. To define the project's approach to quality assurance
B. To appoint external reviewers for quality reviews
C. To define quality criteria in product descriptions
D. To provide administrative support for quality controls
According to the `defined roles and responsibilities' principle, how many categories of stakeholder interest need to be represented in the project management team?
A. One
B. Two
C. Three
D. Six
Which is a purpose of a quality register?
A. To record cross-references to issues relating to the quality of the products
B. To record the date a completed work package was received
C. To provide the status of quality activities carried out for completed products
D. To capture quality concerns about completed products
What process provides information on a team's work to the project manager?
A. Controlling a stage
B. Directing a project
C. Managing a stage boundary
D. Managing product delivery
Identify the missing words in the following sentence. PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.
A. corporate, programme management or the customer
B. the project board
C. the project manager
D. the change authority
During the `initiating a project' process, who specifies the required level of management control?
A. Corporate, programme management or customer
B. Project board
C. Project manager
D. Project assurance
Where can people who join a project after initiation quickly and easily find information about how the project is being managed?
A. Project brief
B. Project initiation documentation
C. Project mandate
D. Project product description
How does the `managing product delivery' process achieve its purpose?
A. By agreeing requirements for how project work should be undertaken
B. By producing highlight reports to enable the project board to oversee the work
C. By requiring the project manager to produce and monitor team plans
D. By escalating issues and risks that cannot be resolved within stage tolerance
Which statement is CORRECT about the customer and suppliers of a project in a commercial environment?
A. Each party may have their own business case for undertaking the project
B. Both parties must apply the same external governance to the project
C. The risk appetite should be collaboratively set before the project starts
D. Management systems need to be unified for successful project delivery
Which is a benefit of using PRINCE2?
A. It promotes consistency of project work and the ability to reuse project assets.
B. It includes techniques for critical path analysis and earned value analysis
C. It enables a project manager to be accountable for the success of a project
D. It prevents any changes once the scope of a project has been agreed
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.