  • Question 811:

    If people other than the Project Board members were doing Project Assurance, who would they report to?

    A. Corporate or programme management
    B. The Project Board member overseeing the relevant area of interest
    C. The Project Manager
    D. The Team Manager whose Work Package execution is being monitored

  • Question 812:

    Which stakeholder interest does the supplier representative represent?

    A. Those who will use the project outputs to deliver forecasted benefits
    B. Those providing administrative services and advice during the project
    C. Those ensuring the project delivers value for money during the project
    D. Those providing maintenance and support services after project closure

  • Question 813:

    Who should act as the communication channel between a project and corporate or programme management?

    A. Project Board
    B. Project Assurance
    C. Project Manager
    D. Project Support

  • Question 814:

    Identify the missing words in the following sentence.

    The first step of [?] is writing the project product description.

    A. PRINCE2's recommended approach to defining and analyzing the products
    B. The `initiating a project' process
    C. Producing the project mandate
    D. PRINCE2's recommended issue and change control procedure

  • Question 815:

    Which is a characteristic of a project?

    A. Are risk free
    B. Have no uncertainty
    C. Are managed as part of business as usual
    D. Are cross-functional

  • Question 816:

    Which role has a specific responsibility for checking that the project remains aligned to the corporate or programme strategy?

    A. Project Manager
    B. Project Assurance
    C. Senior User
    D. Senior Supplier

  • Question 817:

    Which theme defines the accountability for realization of the project's benefits?

    A. Plans
    B. Progress
    C. Organization
    D. Quality

  • Question 818:

    Which level of management in the project management team has the ability to review progress and decide whether to continue, change or stop the project?

    A. Project Manager
    B. Project Board
    C. Team Manager
    D. Corporate or programme management

  • Question 819:

    Which task is performed by the change authority?

    A. Approve a change budget for the project
    B. Approve a request for change within delegated limits
    C. Update the project management team structure when a change is approved
    D. Update the change control approach when a change is approved

  • Question 820:

    When should the Managing a Stage Boundary process be undertaken?

    A. Close to the end of a management stage
    B. After the completion of each management stage
    C. At the end of the final stage
    D. At the end of project start-up

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.