  • Question 781:

    In which process are corrective actions taken to ensure that the management stage remains within tolerance?

    A. Directing a project

    B. Managing product delivery

    C. Controlling a stage

    D. Managing a stage boundary

  • Question 782:

    Which is a purpose of the change budget?

    A. To fund the costs introduced be new requests for change

    B. To fund the increased cost of planned work that exceeds tolerance

    C. To ensure implementation of changes is streamlined

    D. To fund the work to deliver the products to the defined quality criteria

  • Question 783:

    Which describes a purpose of the `starting up a project' process?

    A. To prevent poorly conceived projects from progressing to initiation

    B. To plan delivery of the project's products before committing to significant spend

    C. To approve the customer's quality expectations and defined acceptance criteria

    D. To identify how the project's products will be controlled and protected

  • Question 784:

    What must be assessed throughout the project lifecycle, as a minimum requirement for applying the `risk' theme?

    A. Project threats and opportunities

    B. Performance of the appointed risk owners

    C. How the risk budget is used

    D. Probability impact grid

  • Question 785:

    How should a risk budget be applied?

    A. It is used to fund all aspects of risk assessment and planning

    B. It is used to cover the costs of implementing any contingent plans

    C. It is used to supplement cost tolerance by funding risk activities

    D. It is an explicit budget held outside of the overall project budget

  • Question 786:

    What is the purpose of the project brief?

    A. To trigger the `starting up a project' process

    B. To provide the basis for the `initiating a project' process

    C. To plan the benefits reviews required during the project

    D. To provide a baseline to measure the project against

  • Question 787:

    Which factor should influence the structuring of the project into management stages?

    A. The amount of risk within the project

    B. The availability of the project board

    C. The number of recorded requests for change

    D. The quality process of the organization

  • Question 788:

    Which process has the objective of ensuring that everyone understands who is to be involved in the project's decision making?

    A. Starting up a project

    B. Directing a project

    C. Initiating a project

    D. Controlling a stage

  • Question 789:

    How should a risky and complex project be planned in order to meet the minimum requirements for applying the `plans' theme?

    A. A specific plan must be produced for managing agreed risk responses

    B. The project manager must consider having more management stages

    C. The defined tolerances must be aligned to the project board's risk attitude

    D. A diagram showing the product interdependencies must be produced

  • Question 790:

    Which statement is CORRECT about representatives of the `user' stakeholder interest?

    A. They have to ensure that the project justifies the business investment

    B. They have to ensure that project expenditure provides good value for money

    C. They have the understand the standards that need to be applied

    D. They have to operate the project's outputs during their operational life

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.