Which management level should approve a course of action if project-level tolerance is exceeded?
A. Corporate, programme management or the customer
B. Project board
C. Project manager
D. Team manager
Which process provides information for the project board to review an updated project plan?
A. Initiating a project
B. Controlling a stage
C. Directing a project
D. Managing a stage boundary
How often should the 'controlling a stage' process be used during a project?
A. Once, for the whole project
B. For each delivery stage in the project
C. Whenever the project board meets
D. Twice, for initiation and for the rest of the project
Which is a minimum requirement for applying the 'change' theme?
A. Specify in the change control approach the means by which project products will be protected
B. Document the format and contents of the issue register
C. Produce issue reports to document the impact assessment for requests for change
D. Delegate the change authority to the senior supplier(s) for supplier off-specifications
What is established during the 'initiating a project' process?
A. The agreed protect acceptance criteria
B. The need for a configuration library
C. A plan for the work or project initiation
D. An understanding of the project's funding
Which process is used by the project board to respond to on exception report?
A. Controlling a stage
B. Managing a stage boundary
C. Managing product delivery
D. Directing a project
When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.
A. Defined acceptance criteria
B. the PRINCE2 principles
C. the terminology used
D. the number of themes applied
Which activity is part of the recommended risk management procedure?
A. Allocating a budget to investigate issues
B. Reviewing risk management practices to ensure that they are performing effectively
C. Sending information to stakeholders about risks to the projects
D. Resolving conflicts between the project and the programme board
Which is a minimum requirement when applying the 'risk' theme?
A. To identity and ring-fence an explicit risk budget within the project's budget
B. To describe the probability impact grid in the risk management approach
C. To appoint project assurance to maintain the risk register during initiation
D. To assess if risks might have a material impact on business justification
Why does the project board review the PID during an end stage assessment?
A. To confirm that project controls are adequate for the remainder of the project
B. To notify the commissioning organization that the project has been authorized
C. To review summarized progress to date and decide what to do next with the project
D. To ensure that post project reviews of operational performance are planned
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.