  • Question 711:

    Identify the missing words in the following sentence.

    The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.

    A. project assurance

    B. the project board

    C. the corporate, programme management or the customer

    D. a team manager

  • Question 712:

    Which management product is used to record relationships between specialist products?

    A. Change control approach

    B. Configuration item record

    C. Issue register

    D. Product status account

  • Question 713:

    Which describes a time-driven control?

    A. The dates for the project's end stage assessment included in the project plan

    B. The expected frequency of progress reports specified in a work package

    C. The expected dates for planned checks of specialist products included in a stage plan

    D. The planned exception assessment meeting to authorize a requested exception plan

  • Question 714:

    Which role is responsible for ensuring the project is justified in terms of cost?

    A. Project manager

    B. Executive

    C. Senior user

    D. Senior supplier

  • Question 715:

    Which are purposes of the 'directing a project' process?

    1.

    To enable the project board to be accountable for a project's success by making key decisions

    2.

    To enable the project board to authorize work packages

    3.

    To enable the project board to prepare the communication management approach

    4.

    To enable the project board to exercise overall control of a project

    A. 1 and 2

    B. 2 and 3

    C. 3 and 4

    D. 1 and 4

  • Question 716:

    Which process has the objective of confirming that acceptance criteria have been met?

    A. Controlling a stage

    B. Directing a project

    C. Managing product delivery

    D. Closing a project

  • Question 717:

    When is the 'managing a stage boundary' process used?

    A. Immediately alter the project board has authorized the previous stage

    B. Immediately after the project board has authorized the next stage

    C. Near the end of each stage

    D. Near the end of delivery stages

  • Question 718:

    According to the 'continued business justification' principle, what must project benefits be aligned to?

    A. Regular deliveries throughout the project

    B. The business objectives

    C. The direction of the project board

    D. The technology available

  • Question 719:

    What should be implemented using a risk budget?

    1.

    A request for change

    2.

    A contingent plan

    3.

    Actions to avoid a risk from occurring

    4.

    Responses to dis-benefits

    A. 1 and 2

    B. 2 and 3

    C. 3 and 4

    D. 1 and 4

  • Question 720:

    Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

    A. End stage report

    B. Checkpoint report

    C. Highlight report

    D. Exception report

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.