A few key team members recently left the project team. The remaining members took time to understand the details and found it difficult to make progress. As a result, the project schedule is seriously delayed. What should the project manager do?
A. Request additional resources to be incorporated to the project team.A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned. The SME asks the project manager to write, document and include it in the lessons learned register. What should the project manager do?
A. Assign the documenting task to a project team memberAn insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.
What should the project manager do to get commitment from the sales agents?
A. Use a business case to model a sales pitch and gain consensus from the sponsors.For the purposes of quality assurance a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available.
Why is an attendance list important?
A. It is standard practice on projects to conduct risk review meetings which should have records on meeting attendanceA project manager is working on a project that is required to deliver value on an incremental basis. Which action should the project manager take to enable successful project execution?
A. Identify the tangible and intangible benefits.A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects. What else does the project manager need to do before determining the budget baseline?
A. Look at a previous project to ensure the budget totals match.Which enterprise environmental factors are considered during Estimate Costs?
A. Market conditions and published commercial informationA product owner presented the backlog to the team, and the team raised concerns over implementing some of the features due to various impediments. What should the project manager suggest that the product owner do next?
A. Ensure that the impediments are captured and prioritized based upon the highest valued featuresA project manager is developing the stakeholder register and is having trouble understanding the motivation of some of the stakeholders. What should the project manager do to get this information?
A. Organize a one-on-one conversation with each stakeholder.Five vendors are contributing to a project with an impending deadline. Two vendors are behind on their deliverables and rarely provide status updates.
What should the project manager do?
A. Begin daily check-ins with the two vendors to recover time at their own expense.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.