A project manager is working with the team to deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members, causing negative consequences for delivery.
How should the project manager avoid this situation in the future?
A. Agree with the project team on a suitable collaboration and make sure information is shared at all times.During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager react to ensure the project remains successful?
A. Focus the discussion on recovery and ways to get back on track.A project team is continually being asked by stakeholders to perform rework on their deliverables. The project manager discovers that this is due to poor initial quality.
What should the project manager do?
A. Host a team meeting and ask the team to fix any quality issues immediately since the stakeholders' needs are the main focus.A project manager is leading a project and is asked to negotiate on behalf of their organization. The organization requires that three quotes from different suppliers be obtained before submitting a purchase request to the finance department.
What should the project manager do to align with this requirement?
A. Perform a make-or-buy analysis.A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another.
What should the project manager do?
A. Ask the experienced members to lead the junior members to facilitate skill transfer.A project team has installed software for the client, passed the knowledge to operations, sent the final report, and celebrated. Then 1 week later, the client sendsa list of requirements that have not been met. The client is requesting to fix the issues quickly and within the initial budget.
What should the project manager have done to prevent this from happening?
A. Reviewed the acceptance criteria and obtained client approval.During the design phase of a project, the project manager notices that the schedule performance index (SPI) is 1,8 and the cost performance index (CPI) is 0,1. In a weekly meeting with top management, the project manager reports concerns about these indicators. However, the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project.
What should the project manager do?
A. Monitor the project sponsor but understand that it is normal to spend more money in the design phase of a project.A project is starting with a team that is located all over the world. None of the team members have worked together before. The project goal is ambitious with an aggressive timeline. What should the project manager do?
A. Ask for financial support to set up a physical meeting for the team.A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team. What should the project manager do?
A. Add a user story during sprint planning that gives recognition to behaviors that are aligned with the new valuesA virtual product development team is working well together and is on schedule. One team member wants to take 1 week off to attend a training. What should the project manager do?
A. Decline the team member's request as it might jeopardize the schedule.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.