A scrum master is receiving conflicting status updates for the same task. How should an accurate status be obtained from the team?
A. Review the deliverable carefully and determine the right status.A project manager is assigned to a new project. The project management office (PMO) and the project manager agree that this is the right opportunity to include daily standup meetings. The project team has never used such tools, and a few members are challenging the decision.
What should the project manager do in this situation?
A. Engage an external vendor to perform the design phase under an iterative approach.A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory.
How should the project manager support their claim to the vendor?
A. Share unsuccessful results from previous projects with a similar scopeA final iteration is underway, and a project team is about to complete development. Planning for the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market.
How should the project manager address this issue?
A. Assess the business value impact and review the product roadmap to include any changesA new team member joins the project and fails to apply the project-specific quality assurance (QA) processes.
What should the project manager have done to avoid this issue?
A. Obtained external training in quality assurance (QA) for the new team member.One deliverable for a project is to translate and print materials for students every 2 weeks. Printing services are available but without guaranteed timelines because other projects generate significantly higher profits and have a higher priority. What should the project manager do to mitigate the risk of not having the materials printed on time?
A. Meet with the manager to set a high priority for printing the materialsA project manager identified a risk on a deliverable completed by a contractor and added it to the risk register. During the last inspection meeting for the deliverable, the project manager notices that the suggested mitigation did not produce the expected results.
How should the project manager proceed?
A. Review the procurement performance to identify the root cause.A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project's value and caused a delay in the approval.
What should the project manager have done to avoid this setback?
A. Assessed feasibility and impactsWhile a project manager is trying to build the first baseline for a project, a change request is being sent from one of the functional managers. What should the project manager do?
A. Discuss this with the functional manager and related parties.A project manager is in the beginning stages of delivering a project and is assessing and prioritizing identified risks.
What should the project manager do next?
A. Plan the risk responses and assign risk response owners.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.