  • Question 791:

    A customer has given a project team several requests for new features on a product. The customer is upset that the requests have been placed in the backlog and are not currently being worked on by the team. What should the team do next?

    A. Review the feature requests and reject the most complex ones.
    B. Organize the feature requests from simple to complex.
    C. Prioritize the requests for the next sprint.
    D. Turn the requests into user stories and prioritize them.

  • Question 792:

    An agile project manager has noticed their teams declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?

    A. Develop a reward system related to position and years of experience.
    B. Clarify project goals and project contract constraints.
    C. Promote cross-training and mentoring among team members.
    D. Introduce performance standards and evaluation methods.

  • Question 793:

    Which of the following is an Agile improvement technique to address issues continuously, e.g. after daily stand-up?

    A. Retrospectives
    B. Verification Sessions
    C. Intraspectives
    D. Futurespectives

  • Question 794:

    Which of the following is critical for the success of distributed Agile teams?

    A. Cost containment
    B. High volume of communication
    C. Shared knowledge
    D. Culture of collaboration

  • Question 795:

    What is a specific development practice that has been effective in implementing disciplined DevOps?

    A. Put the client first.
    B. Create a safe environment.
    C. Practice continuous delivery.
    D. Manage risk.

  • Question 796:

    If the Development Team does not have all the skills to accomplish the Sprint Goal, the Scrum Master should:

    A. Cancel the Sprint
    B. Stop using Scrum
    C. Have the development team determine the definition of "Done" and work through the Sprint backlog
    D. Remove the impacted stories from the Sprint backlog

  • Question 797:

    A technical problem arises that will likely impact the stories planned for delivery in the current sprint. What should the scrum master do?

    A. Consider adding a story to the next sprint to seek resolution
    B. Immediately solve the problem on behalf of the team
    C. Ask the team to collaboratively work out a solution
    D. Engage a technical manager to assist with finding a solution

  • Question 798:

    What is the best definition of "Done"?

    A. Whatever will please the Product Owner
    B. It is determined by the Scrum Master
    C. The prodct has passed QA and has all of the required release documentation
    D. The definition of "Done" is one that would allow the development work to be ready for a release.

  • Question 799:

    One of the overseas stakeholders on an agile project has not been actively involved in the project's development. What would be the first step to reengage the stakeholder?

    A. Increase the frequency of emails and/or try to call the stakeholder.
    B. Remind the stakeholder of their obligation to engage in the project.
    C. Talk to the stakeholder's superior so they can offer coaching and guidance on project involvement.
    D. Set up a meeting with the stakeholder to modify the working agreement and ensure future engagement.

  • Question 800:

    Which following statement is the least accurate regarding the Burndown chart?

    A. It is calculated using hours or points
    B. It is updated by the development team daily
    C. It provides insight into the quality of the product
    D. It reflects work remaining

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-ACP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.