CompTIA PK0-005 Online Questions & Answers

  • Question 361:

    An opportunity emerged in the middle of a project life cycle.

    Which of the following is the BEST action for the project manager to take?

    A. Exploit the risk.
    B. Accept the risk.
    C. Avoid the risk.
    D. Transfer the risk.

  • Question 362:

    A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?

    A. Project scope
    B. Quality plan
    C. Contract obligations
    D. Work breakdown structure

  • Question 363:

    A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).

    A. Train users on the proper use of the system.
    B. Escalate the issue to the CCB
    C. Hold sessions to understand user challenges.
    D. Track system usage and report user activity.
    E. Log the issue in the project risk register.
    F. Create a memorandum of acceptable use.

  • Question 364:

    During project initiation, a project manager needs to identify goals and deliverables that should be completed by the end of the project and also meet certain cost and time factors.

    Which of the following would best align with these needs?

    A. Work breakdown structure
    B. Change log
    C. Project success criteria
    D. Milestone chart

  • Question 365:

    Project A and Project B share a team member. The team member is falling behind on a task for Project B.

    Which of the following is the BEST action to take to get the task for Project B back on track?

    A. Negotiate to get more of the team member's available time.
    B. Assign the team member to work overtime to finish the task.
    C. Speed up completion of the task by assisting the team member.
    D. Have the project manager complete the task.

  • Question 366:

    A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?

    A. Escalate the communication issues.
    B. Implement a communication platform.
    C. Review the communication plan.
    D. Talk with the head of the PMO.

  • Question 367:

    A project manager is concerned about the performance of a developer who is struggling with the new coding language. Which of the following actions should the project manager take?

    A. Send a request to the project sponsor to add an additional developer.
    B. Provide the developer with only non-critical tasks.
    C. Assign the developer training to improve the developer's skills.
    D. Remove the developer from the project team.

  • Question 368:

    Which of the following can a project manager infer from the following velocity chart?

    A. The project is on schedule.
    B. The project Is ahead of schedule.
    C. The project is behind schedule.
    D. The project is at risk.

  • Question 369:

    Given the following velocity chart:

    Which of the following updates on the project status should the Scrum master provide to the senior management team?

    A. The project utilized all of its available reserve.
    B. The project has scope creep.
    C. The project deviated from the critical path.
    D. The project is trending ahead of schedule.

  • Question 370:

    Which of the following would a scrum team discuss during a daily stand-up meeting?

    A. The likelihood of uncertain events occurring, the impact of the uncertain events, and the responses to take
    B. Actions to continue, actions to stop, and recommendations on how to proceed in the future for similar endeavors
    C. Buffer utilization and reallocation, critical resources with schedule impacts, and path convergence coordination
    D. Progress from the previous day, projected accomplishments for today, and foreseen issues that may interfere with work

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.