  • Question 521:

    A project manager has laid out a network diagram and is beginning to schedule activities for an upcoming project. Which of the following activities should be performed LAST?

    A. Determine the start/finish dates.
    B. Determine the critical path.
    C. Determine the dependencies.
    D. Determine the task durations.

  • Question 522:

    Which of the following documents should be used FIRST when addressing a vendor that is not complying with the project deliverables?

    A. SLA
    B. Project charter
    C. Risk register
    D. RFP

  • Question 523:

    A project team is executing a transition plan for a project. During which of the following project phases does this normally occur?

    A. Execution
    B. Monitor and control
    C. Closing
    D. Planning
    E. Initiation

  • Question 524:

    A project team learns that potential remodeling on the production floor might occur during the execution phase of their project. The project team starts debating the different options available to keep delivering without adjusting the schedule. Which of the following risk activities is being performed?

    A. Mitigation
    B. Quantification
    C. Planning
    D. Identification

  • Question 525:

    A team member has completed an assigned task. Which of the following roles should be notified FIRST?

    A. Project sponsor
    B. Key stakeholders
    C. Project manager
    D. Project team

  • Question 526:

    The project team has identified all the tasks needed to create project deliverables and grouped them into work packages covering all project scope. Which of the following should be done NEXT?

    A. Identify task relationships.
    B. Put the resources on tasks.
    C. Set the quality gates.
    D. Estimate the work package.

  • Question 527:

    A stakeholder is unaware of a project's status.

    Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)

    A. Status report
    B. Organizational chart
    C. RACI matrix
    D. Meeting minutes
    E. Communication plan

  • Question 528:

    Which of the following is primarily responsible for developing the timeline?

    A. Project sponsor
    B. Project coordinator
    C. Project manager
    D. Project scheduler

  • Question 529:

    The project's network map has a loop with multiple project outcomes.

    This is the result of which of the following scheduling tools?

    A. Establishing project schedule baselines
    B. Critical Path Analysis
    C. Critical Chain Method
    D. Graphical evaluation and review technique

  • Question 530:

    A project manager is implementing a new edition of a magazine with an end-of-the-week deadline. The design analyst notices two main articles were not included, as requested by the client. Which of the following constraints should be considered FIRST?

    A. Scope
    B. Quality
    C. Time
    D. Budget

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.