  • Question 111:

    A fire occurred in the production facility over the weekend, affecting the machinery being used to produce a deliverable. No injuries were reported.

    Which of the following is MOST appropriate for the project manager to do NEXT?

    A. Refer to the contingency plan
    B. Conduct an immediate emergency team meeting
    C. Perform a SWOT analysis D. Implement the risk response plan

  • Question 112:

    Which of the following are examples of organizational change? (Choose two.)

    A. Relocation
    B. Scope
    C. Business process
    D. Schedule
    E. Risk event

  • Question 113:

    Rather than sending emails to communicate all project information, the project manager:

    1.

    Makes telephone calls to key stakeholders for urgent information

    2.

    Sends emails for routine information

    3.

    Posts on the project intranet site for required but minimally used information

    Which of the following BEST represents what the project manager is doing?

    A. Prioritizing based on personal preferences
    B. Tailoring the method based on message content
    C. Adjusting the method based on confidentiality constraints
    D. Demonstrating concern for technological factors

  • Question 114:

    As part of the early stages of a potential corporate acquisition, which of the following documents should the acquiring organization complete, showing regulators and investors the offered purchase price and target closing date?

    A. Sales contract
    B. Memorandum of agreement
    C. Letter of intent
    D. Purchase order

  • Question 115:

    An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast-tracked tasks that require additional hours. Which of the following documents did the project manager fail to reference?

    A. MOU
    B. MOA
    C. SOW
    D. SLA

  • Question 116:

    A construction company has not been on the job for more than two weeks. Which of the following is an example of how a project manager can utilize the transfer risk strategy?

    A. Changing the schedule to accommodate a new finish date
    B. Hiring a new company to complete the work
    C. Calling the project sponsor to explain the situation
    D. Requiring the construction company to send new employees

  • Question 117:

    During a project, the purpose of examining the cost baseline is to:

    A. organize payment of the bills
    B. determine the minimal cost of the project
    C. anticipate the total planned costs
    D. compare against the total planned income

  • Question 118:

    Which of the following can a project manager use to keep track of finances and ensure costs are accurately applied to a project?

    A. PO numbers
    B. Cost baseline
    C. Bill of materials
    D. WBS codes

  • Question 119:

    During a meeting, a new member of the PMO says, “If this project fails, then the portfolio fails, and the program as a whole ultimately fails.” Which of the following errors is the new PMO member making?

    A. The new PMO member has not review the intra organizational strategy.
    B. The new PMO member does not realize that although a project can fail, a program cannot, as it contains all projects in a company.
    C. The new PMO member has confused the relationship between portfolio and program.
    D. The new PMO member has not had an opportunity to review the company's project list.

  • Question 120:

    Which of the following is described as placing responsibility for addressing the potential effects of an uncertain future event on an entity outside the organization?

    A. Risk avoidance:e
    B. Risk transfer
    C. Risk exploitation
    D. Risk mitigation

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-004 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.