Question 1 Single choice

Which of the following types of closure occurs when a project has been delivered to the satisfaction of all parties?

  1. A

    Project post mortem

  2. B

    Project cancellation

  3. C

    Project phase closure

  4. D

    Project completion

Show answer and explanation

Correct answer: D

Question 2 Single choice

A project manager has a project with staff in four different countries.

When generating the resource management plan, which of the following should be considered FIRST?

  1. A

    Reviewing holiday and vacation schedule with all team members.

  2. B

    Getting the email address of all the employees.

  3. C

    Locating each employee on the map in the office.

  4. D

    Understanding the international country code of all the team members.

Show answer and explanation

Correct answer: A

Question 3 Single choice

A project team member, Joe, has completed his project work. Although the project is not completed yet, Joe has been assigned by the PMO director to a new project.

Which of the following describes the organization structure Joe works in?

  1. A

    Functional

  2. B

    Matrix

  3. C

    Project based

  4. D

    Strong Matrix

Show answer and explanation

Correct answer: C

Question 4 Single choice

Which of the following is typically the LAST step when acquiring a product or service from a vendor?

  1. A

    Vendor selection

  2. B

    Evaluate seller response

  3. C

    Contract development

  4. D

    Contract signing

Show answer and explanation

Correct answer: D

Question 5 Single choice

As a result of changes in the economy, it has been communicated that the current costs for needed components have doubled from what was originally budgeted. If the procurement occurs, this would result in exceeding the cost baseline for the project.

Which of the following actions should the project manager take?

  1. A

    Evaluate alternatives that could be used that would result in the same scope to be produced

  2. B

    Use contingency funds to cover the procurement of the components

  3. C

    Create a change request to see if the baselines can be revised to incorporate the appropriate costs

  4. D

    Contact the customer to let them know that the costs will be higher, and await approval from the customer before proceeding

Show answer and explanation

Correct answer: A

Question 6 Single choice

After a project team has almost completed the development on the project's original requirements, the users identify functionality that is necessary but was not in the original requirements. The project manager MUST:

  1. A

    Update the risk register.

  2. B

    Implement the change.

  3. C

    Cancel the project.

  4. D

    Generate a change request.

Show answer and explanation

Correct answer: D

Question 7 Single choice

The formula for Schedule Performance Index (SPI) is:

  1. A

    SPI = SV/PV

  2. B

    SPI = EV/PV

  3. C

    SPI = EV/SV

  4. D

    SPI = PV/EV

Show answer and explanation

Correct answer: B

Question 8 Single choice

Which of the following are included in operational process compliance?

  1. A

    Audit trails, retention, and version control

  2. B

    Local, state, and federal laws

  3. C

    Tollgate approval, project phase transition

  4. D

    Change control board, committee consulting

Show answer and explanation

Correct answer: A

Question 9 Single choice

Which of the following is crucial to scope management?

  1. A

    A Work Breakdown Structure dictionary

  2. B

    A final statement of project objectives

  3. C

    An automated scope management system

  4. D

    A formal change management process

Show answer and explanation

Correct answer: D

Question 10 Single choice

Which of the following BEST describes the general idea of the project?

  1. A

    Project objectives

  2. B

    Project milestones

  3. C

    Project assumptions

  4. D

    Project scope

Show answer and explanation

Correct answer: A