  • Question 41:

    Which of the following describes the work package level of a WBS?

    A. Project phases
    B. Major deliverables
    C. The lowest level
    D. The project name

  • Question 42:

    In a functional structured organization, which of the following is a common cause of conflict with project team members?

    A. Inadequate budget
    B. Failure to communicate project goals and objectives
    C. Competing demands for resources
    D. Lack of proper training

  • Question 43:

    Which of the following is an advantage of using GERT?

    A. Discretionary dependencies can be used
    B. Allows using dummy activities
    C. Slack time is more easily shown
    D. Multiple outcome options can be shown

  • Question 44:

    Which of the following components of a quality management plan is an initial quality measurement?

    A. Quality specifications
    B. Quality control
    C. Quality assurance
    D. Quality baseline

  • Question 45:

    Resources for a project report to a project manager and a functional manager. The organizational structure is:

    A. Matrix
    B. Ad hoc
    C. Functional
    D. Projectized

  • Question 46:

    Which of the following is the primary purpose of a WBS?

    A. To track project milestone completions
    B. Show project tasks scheduled for a specific time period
    C. Decomposition of the project deliverables
    D. Assign specific tasks to project team members

  • Question 47:

    Which of the following is a component of a performance evaluation for an individual?

    A. Resource utilization
    B. Role assessment
    C. Scope management
    D. Variance management

  • Question 48:

    The IT department is currently resource constrained managing daily operational tasks. However, there are a number of subject matter experts (SME) within the department who are critical to making the project succeed. Which of the following should the project manager use to ensure the success of the project?

    A. Engage a services company to deliver the project
    B. Negotiate staff augmentation with the SME's managers
    C. Recruit staff form the organizations strategy area
    D. Perform a request for proposal

  • Question 49:

    All of the following are characteristics of a project EXCEPT that it:

    A. is managed by consensus.
    B. is a temporary endeavor to create a unique product or service.
    C. is limited by human and financial resources.
    D. adheres to the triple constraint.

  • Question 50:

    Which of the following tools would a project manager use to determine the root cause of an issue?

    A. Pareto Chart
    B. Ishikawa Diagram
    C. Histogram
    D. Monte Carlo Analysis

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.