As the production scheduler at a manufacturing company that does not use advanced warehousing, you have firmed a planned production order from master planning. The order is now ready for processing.
What should you do first in production control?
A. Start the order.DRAG DROP
A manufacturer sends wiring harnesses to a vendor to be soldered to a connector.
You create the subcontracting process in the bill of materials (BOM) and route to account for the items sent to the vendor.
You need to set up a new item model group for the service item.
Which three actions should you perform? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place:

A company produces multiple products that require an installation kit that includes 50 components.
The company does not want to include these 50 components in every Bill of materials (BOM).
You have a BOW kit that includes all SO components, but you do not want it to produce a separate production order.
You need to set up the product BOM for the finished good.
What should you do?
A. Change the coverage group on the kit item to Manual.HOTSPOT
A company sells chemicals that require special instructions for disposal and remediation due to toxicity regulatory requirements.
The company requires that when a sales order's packing slip is printed for a product that contains a toxic chemical, the instructions must also be printed for inclusion in the shipment.
You need to configure the system to meet the requirements.
Which configurations should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item.
The item has the following Lean setup:
1. The setup uses a Lean schedule group with a throughput ratio=2
2. The process activity tied to production flow has the following runtime activity times: time=3 min, per quantity=1
3. The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8-hour day)
4. The throughput is 10 per hour
You need to set up a Discrete operation to mirror the item's production flow activity.
What should you do?
A. Create a route with a runtime =1, a process quantity =6, and the operation's hours/time =1DRAG DROP
A manufacturer uses route operations and job scheduling.
You use a unique calendar for a conveyor line.
The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns.
You must make a temporary change to the number of hours the resource is available.
You need to adjust the efficiency percentage for the conveyor line calendar.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place:

You are configuring the production floor execution interface in Dynamics 365 Supply Chain Management.
The current configuration of the production floor execution interface hinders efficient production floor operations and impedes worker productivity.
You need to optimize the production floor execution interface configuration.
What should you do?
A. Enable Use the actual time of registration and Single worker.HOTSPOT
A company uses Dynamics 365 Supply Chain Management. Technicians travel to several facilities to complete routine maintenance on equipment.
The company recently invested in new equipment. The technicians have no experience maintaining the new equipment. The technicians must be able to perform the following activities:
You need to configure features to assist the technicians.
Which features must you configure? To answer, select the appropriate options in the answer area.

You are a production manager at a company which produces large batches of coffee and creamers.
After a quality inspection, batch 120008 of your cold brew coffee (item number CB-0001) was found to be too acidic and must be reworked.
You need to add 20 grams of sugar and stir the product for an additional 0.S hours.
What three actions are required on the rework order? Each correct answer presents pan of the solution.
NOTE: Each correct selection is worth one point.
A. Manually reserve batch 120008 after estimating the batch order.A manufacturer is implementing master planning in Dynamics 365 Supply Chain Management for planned orders.
Master planning is running for the first time in the production environment.
You need to instruct the production planners where to view the following information:
In which two possible locations can the information be found? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
A. Sequenced planned ordersNowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your MB-335 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.