DRAG DROP
A company is implementing Dynamics 365 Supply Chain Management
The company is a subcontractor that produces subassemblies for two major customers. CustomerA and Customers
The company prioritizes CustomerA production orders to start on Mondays.
The production orders may take several days to complete.
Customers' orders are produced throughout the week, after CustomerA orders are completed.
Work in process (W1P) must be calculated and consolidated for CustomerA and CustomerB respectively on the financial reports.
You need to configure the production requirements.
What should you configure? To answer, drag the appropriate configurations to the correct requirements. Each configuration may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
Select and Place:

HOTSPOT
A company has implemented Dynamics 365 Supply Chain Management and is setting up a new production line for a product.
This production line will operate in three shifts, five days a week, with each shift producing 100 widgets.
Each machine on the line performs specific functions in a sequenced manner, and the process requires a qualified machinist.
One of the machinists, who rotates between machines, needs time off for appointments every Tuesday and Thursday afternoon.
You must be able to track the availability of both the rotating machinist and each machine, as well as schedule production orders based on the available capacity.
You need to configure the route accordingly.
Which configuration options should you select? Note: Each correct selection is worth one point.

A beverage company uses Dynamics 365 Supply Chain Management batch processing for production-
You need to identify the ingredient type used in batch processing when the base attribute of a product is added to a formula line.
What is the ingredient type?
A. activeA company has three jobs in a job queue. JobB and JobC start while JobA is in progress. The following table shows the estimated production time for each job.

The actual work hours and total bundle time are shown in the following table.

You need to calculate the allocated time for JobA by using a job allocation key.
What is the total allocated time for JobA?
A. 1 hourDRAG DROP
You need to configure the reservation methods prototype production order as planned by the engineering team.
How should you configure the prototype production order?
To answer, move the appropriate configurations to the correct requirements. You may use each configuration once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
Select and Place:

HOTSPOT
A company that assembles packaging material uses Dynamics 36S Supply Cham Management.
The glue that is used in assembly has run out of stock and will not be back in stock as expected.
Another adhesive must be substituted for the glue. This will affect orders in planning as well as production orders that have started.
You need to ensure that the substitute adhesive is used in production until the glue is back in stock.
Which configuration should you use for each requirement? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection Is worth one point.

You have a product that can be manufactured on two different production lines in the same warehouse. You create resources and then create individual input locations for the resources. You create two routes.
Each route uses different resources.
Materials are staged for consumption in different locations based on the resources being utilized for production.
You need to set up the formula to consume the goods from the correct line-side location.
What should you do?
A. Select a warehouse and consumption operation for each line.A company produces pipe at certain fixed lengths.
The company must be able to schedule cutting machines. You set up the cutting machines as resources. AH cutting resources can produce many of the products.
There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.
You need to configure the resources to account for these different products.
What should you do?
A. Build capability related to length and assign to the appropriate resources.DRAG DROP
A recreational vehicle (RV) manufacturing company is implement Dynamics 365 Supply Chain Management.
All RVs are configured to order.
Quality checks show that there is an issue with the sealant used with the windows in some of the RVs.
You need to identify which RV models use the sealant and change the sealant item.
Which function should you use for each requirement?
To answer, drag the appropriate functions to the correct requirements. Each function may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
Select and Place:

HOTSPOT
You need to resolve the issue for UserG.
What should you do? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your MB-335 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.