JK0-017 Exam Details

  • Exam Code
    :JK0-017
  • Exam Name
    :CompTIA E2C Project+
  • Certification
    :CompTIA Certifications
  • Vendor
    :CompTIA
  • Total Questions
    :402 Q&As
  • Last Updated
    :Jul 12, 2026

CompTIA JK0-017 Online Questions & Answers

  • Question 121:

    Which of the following is the purpose of a Pareto diagram?

    A. To show the sequence in which work will be performed
    B. To create the process that will complete the project
    C. To determine the critical path
    D. To direct team efforts to the areas that will have the most impact

  • Question 122:

    Which of the following quality option costs BEST identifies the expense of inspecting deliverables to prevent flawed products from reaching the customer?

    A. Actual costs
    B. Failure costs
    C. Appraisal costs
    D. Contract costs

  • Question 123:

    A project manager receives a request for a minor change to one of the deliverables. Which of the following documents would MOST likely be impacted?

    A. Work Breakdown Structure (WBS)
    B. Project charter
    C. Communication plan
    D. Quality plan

  • Question 124:

    The project has an AC of $5,000. Which of the following would be used to determine the budget needed to complete the project?

    A. ETC
    B. PV
    C. BAC
    D. EAC

  • Question 125:

    Which of the following conclusions can be drawn when a project has a CPI of 1.2?

    A. The project is taking longer than the estimated schedule.
    B. The project is costing less than the estimated budget.
    C. The project is taking less time than the estimated schedule.
    D. The project is costing more than the estimated budget.

  • Question 126:

    A project manager is analyzing the network schedule to determine the early start and early finish dates as well as the late start and late finish dates, for each activity. The project manager is not taking into account any resource constraints. Which of the following methods is demonstrated in this scenario?

    A. Critical Chain Method (CCM)
    B. Precedence Diagramming Method (PDM)
    C. Arrow Diagramming Method (ADM)
    D. Critical Path Method (CPM)

  • Question 127:

    A project manager was asked to complete a project three weeks early and not crash the project. Which of the following should be done?

    A. Move some of the task to another release.
    B. Have the team work over time and give them time off later to save the budget.
    C. Continue to work and complete the project as soon as possible.
    D. Review the plan with the team and develop a way to reduce the time

  • Question 128:

    Which of the following shows a project that is presently over its financial budget?

    A. CPI = 1.4
    B. CPI = 0
    C. CV = +$11,000
    D. CPI = 0.8

  • Question 129:

    The EV of a particular project is $6 million. The CV is -$340,000. Which of the following can be determined from this information?

    A. The project costs are currently under-budget.
    B. The AC is less than the EV.
    C. The EV is higher than the AC.
    D. The project costs are currently over-budget.

  • Question 130:

    Which of the following are created using information contained in the work breakdown structure (WBS)? (Select Two).

    A. Project scope statement
    B. Project statement of work
    C. Project charter
    D. Project activity estimates
    E. Project resource estimates

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.