ISTQB ISTQB-CTAL-TM Online Questions & Answers

  • Question 121:

    Which of the following Is the common set of information to be produced in a test estimate?

    A. Number of people number of systems lines of code, cost
    B. Time per person budget end date start date
    C. Test effort test duration time to complete, cost
    D. Effort time cost, test activities

  • Question 122:

    It is now the final day of the planned user acceptance test period and you are preparing the test completion report. Some defects have not been fixed and some tests have not been run; due to both these factors the exit criteria have not been

    met.

    Which two of the following metrics will be most useful in helping the stakeholders to decide whether to allow the system into production?

    A. Breakdown by priority of tests not run
    B. Breakdown by severity of estimated residual defects
    C. Breakdown by priority of outstanding requirements
    D. Breakdown by risk level of outstanding risks
    E. Breakdown by severity of unfixed defects

  • Question 123:

    Your organization is considering using open-source tools. You have been told you need to be aware of the terms of the GNU general public license. What is the basic concept of this license? [1]

    A. Anyone can use the software anytime for any reason.
    B. A small license fee must be paid to the supplier of the software.
    C. If you're going to distribute the software, you need to do so with the same terms as were applied when you received the software.
    D. You are allowed to use the software internally, but it cannot be incorporated into any product for which you will receive a profit.

  • Question 124:

    Which TWO of the following metrics will be MOST useful in helping the stakeholders to decide whether to allow the system into acceptance testing?

    1. Breakdown of all risks by status (closed / not fully tested / one or more tests failed)

    2. Breakdown by test priority of test execution status (passed / failed / not run)

    3. Breakdown of outstanding risks by risk level and status (not fully tested / one or more tests failed / both)

    4. Breakdown of unresolved defects by severity and status

    5. Breakdown of unresolved defects by Risk Id/s that is/are affected by them

    A. 3and4
    B. 2and5
    C. 1 and4
    D. 1 and2

  • Question 125:

    It has been agreed that the following test planning documents will be produced

    A single overarching document outlining the general testing methodology for the whole programme of work A subordinate test plan for each of the three projects A separate test plan for performance testing within each project

    Which one of the following options BEST describes the type of test management document that will meet the programme requirements?

    A. Option 2.
    B. Option 4.
    C. Option 1.
    D. Option 3.

  • Question 126:

    Your company is installing a third-party enterprise-wide business software package. This is the first time the company has done anything like this. Which technique would be the best one to use to estimate the testing effort? [3]

    A. Estimated developer effort and lines of code
    B. Industry averages
    C. Review of the installation guide
    D. Past experience with in-house projects

  • Question 127:

    Which of the following BEST explains how test process improvement can benefit an organisation? SELECT ONE OPTION

    A. It can result in defect free releases into production
    B. It can reduce the demand for test resources to support maintenance releases.
    C. It can prevent developers making errors when writing code.
    D. It can increase the number of applicants for job vacancies.

  • Question 128:

    The Test Manager must assemble team members that have which of the following characteristics? [1]

    A. Thrive in a routine, structured environment
    B. Will not change the severity of a defect report
    C. Will spark informal cross training among themselves
    D. Possess identical skill sets

  • Question 129:

    Which of the following should be considered the biggest risk to the schedule when trying to implement formal scripted test cases early in the SDLC for a system with a large GUI front end? [2]

    A. Early implementation might uncover errors in the design documentation.
    B. Test maintenance might be required due to changes in the presentation layer.
    C. The testers will be working on analysis and design early in the schedule.
    D. The developers may feel pressured not to change anything.

  • Question 130:

    Which two items are MOST relevant for inclusion in your tool selection plan for functional test automation in Agile?

    A. Demonstrating that the tool will deliver a positive ROI for the project
    B. Nominating the person who will be responsible for the tool
    C. Estimating the costs of the tool evaluation and selection process
    D. Demonstrating that only one tool will be needed
    E. Anticipating the risks to achieving positive ROI with the tool

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only ISTQB exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your ISTQB-CTAL-TM exam preparations and ISTQB certification application, do not hesitate to visit our Vcedump.com to find your solutions here.