Question 1 Single choice

It the lest manager must repeatedly step in to resolve conflicts within the team what phase is the team in and what competencies are required from the test manager?

  1. A

    Forming Professional

  2. B

    Storming Social

  3. C

    Norming Personal

  4. D

    Performing Methodological

Show answer and explanation

Correct answer: B

Explanation

Understanding Team Development Phases:
TheStormingphase is where team members often experience conflicts as they establish their roles and relationships.
Resolving conflicts in this phase is essential for team cohesion and productivity.

Competencies Required:
Social competenciesare needed to mediate, facilitate communication, and encourage collaboration.
Evaluation of Options:
A. Forming Professional:
Incorrect. The Forming phase involves team orientation, not conflict resolution.
B. Storming Social:
Correct. This phase requires social skills to address conflicts and foster a productive environment.
C. Norming Personal:
Incorrect. The Norming phase focuses on team cohesion and process standardization.
D. Performing Methodological:
Incorrect. The Performing phase assumes the team is high-functioning and requires minimal intervention.
Syllabus Alignment:
ISTQB emphasizes understanding team dynamics and applying social skills for effective team management during challenging phases (TM-3.1.5).
References:
ISTQB Advanced Level Test Management Syllabus (TM-3.1.5)

Question 2 Single choice

The test team is using a distributed model for testing.

What is the primary factor you should consider with this model? [1]

  1. A

    Alignment of methodologies

  2. B

    Co-location of test team

  3. C

    Provision of growth opportunities for the individual testers

  4. D

    Planned vs. actual hours

Show answer and explanation

Correct answer: A

Explanation

A distributed model for testing is a testing model that involves testers working in different locations, time zones, or organizations, such as onshore, offshore, or nearshore 1. The primary factor that you should consider with this model is the alignment of methodologies, which means that the testers follow the same or compatible testing processes, standards, tools, and techniques, regardless of their location, time zone, or organization 2. The alignment of methodologies can help to ensure the consistency, quality, and efficiency of the testing activities, as well as to facilitate the communication, coordination, and collaboration among the testers 3. Therefore, option A is the correct answer.
Option B is incorrect because co-location of test team is not a factor that you should consider with a distributed model for testing, but rather a factor that is contrary to a distributed model for testing. Co-location of test team means that the testers work in the same physical location, which can have some advantages, such as easier communication, faster feedback, and stronger team spirit, but also some disadvantages, such as higher costs, limited resources, and less diversity 4.
Option C is incorrect because provision of growth opportunities for the individual testers is not a factor that you should consider with a distributed model for testing, but rather a factor that is relevant to any testing model. Provision of growth opportunities for the individual testers means that the testers are given the chance to learn new skills, gain new experiences, and advance their careers, which can have some benefits, such as increased motivation, productivity, and retention of the testers.
Option D is incorrect because planned vs. actual hours is not a factor that you should consider with a distributed model for testing, but rather a factor that is relevant to any testing model. Planned vs. actual hours is a testing metric that compares the estimated and the actual effort spent on the testing activities, which can help to measure the accuracy of the test estimation, the efficiency of the test execution, and the variance of the test schedule.
References:
1: ISTQB Glossary, Distributed Testing
2: Distributed Testing - Software Testing Fundamentals
3: ISTQB Advanced Level Test Manager Syllabus, Section 3.2.1
4: Co-located vs.
Distributed Teams: What's the Difference? : How to Provide GrowthOpportunities for Employees : Software Testing Metrics: What is, Types & Example

Question 3 Single choice

Which three of the following would be considered a good mix of technical and interpersonal skills (hard and soft), for a test team leader? a- Ability to compliment a developer. b- Presenting information regarding a test project progress to stakeholders c- Using a configuration management tool. d- Ability to read a development coding language e- Assessing a failure and documenting it correctly.

  1. A

    c.d and e.

  2. B

    a.b and e.

  3. C

    a.c and d.

  4. D

    b, d and e.

Show answer and explanation

Correct answer: D

Question 4 Single choice

You are the Test Manager for a software house (SoftTech), who provide a core banking product to retail banks around the world to enable their customers to process payments via the Internet and telephone banking.
Your current project is to integrate SoftTech's core banking product with Welsh Bank's existing bank systems. However, Welsh Bank's systems are maintained by experienced developers and are poorly documented.

Welsh Bank has stated that this project must comply with Financial Conduct Authority (FCA) regulatory banking standards.
A specification for the 10 interfaces to Welsh Bank's existing systems has been produced by SoftTech's development team.

You have been asked to plan and conduct reviews for the system integration and support documentation of all the systems. Which of the following is the BEST approach for this project? SELECT ONE OPTION

  1. A

    Conduct Inspections to verify that all documentation conforms to a set standard.

  2. B

    Conduct a management review to assess progress of the integration features.

  3. C

    Conduct an audit to verify that all test deliverables have been produced and signed off.

  4. D

    Conduct an informal review of the integration documentation before the systems are integrated.

Show answer and explanation

Correct answer: A

Question 5 Single choice

Which of the following Is the common set of information to be produced in a test estimate?

  1. A

    Number of people number of systems lines of code, cost

  2. B

    Time per person budget end date start date

  3. C

    Test effort test duration time to complete, cost

  4. D

    Effort time cost, test activities

Show answer and explanation

Correct answer: D

Explanation

Key Factors in Test Estimation: Test estimation requires identifying measurable factors that influence the testing process, includingeffort (workload in person-hours),time(calendar duration),cost, and thespecific test activities(e.g., planning, design, execution).
These are critical to align resources and schedules, ensuring effective project management.
Evaluation of Options:

Ais incorrect: While "lines of code" may relate to testing scope in specific cases, it is not universally applicable in test estimation.
Bis incorrect: "Start and end dates" are outputs of planning, not estimation.
Cis partially correct but lacks a focus on "test activities," which is crucial for completeness.
Dis correct as it covers effort, time, cost, and test activities, reflecting a comprehensive test estimate.
References and Syllabus Alignment: As per ISTQB Advanced Test Management syllabus, test estimation should consider effort, time, cost, and activities under "Test Planning" (TM-1.1.1).

Question 6 Single choice

Your team has been assigned to test a loyalty card program for a supermarket chain. Because this is a highly competitive market significant investment has been made to determine the shortcomings of the products offered by competitors While the feature sets are mostly the same, there is a wide variance In usability and performance and the users perceptions of these quality characteristics.
Given only this information what test approach would be most appropriate?

  1. A

    Model-based

  2. B

    Experience-based

  3. C

    Risk-based

  4. D

    Requirements-based

Show answer and explanation

Correct answer: C

Explanation

Context Analysis:
Evaluation of Test Approaches:
A. Model-based:
Incorrect. This approach is used for validating predefined models, not addressing specific usability and performance risks.
B. Experience-based:
Incorrect. Useful for exploratory testing but does not directly align with prioritizing and addressing risks.
C. Risk-based:
Correct. Focuses on identifying and mitigating the highest risks, such as usability and performance in this context.
D. Requirements-based:
Incorrect. Emphasizes functional completeness, not specific quality characteristics like usability or performance.
Syllabus Alignment:
Competitive market conditions emphasize the importance of usability, performance, and user perceptions, highlighting risks to user satisfaction and product success.
ISTQB Advanced Test Management syllabus highlights risk-based approaches as effective for addressing high-impact quality characteristics (TM-1.3.4).
References:
ISTQB Advanced Level Test Management Syllabus (TM-1.3.4)=========================

Question 7 Single choice

You are managing the testing for a bank card project. The testing was scheduled to take 10 weeks but by the time the software was developed only six weeks were available for testing Knowing there were a lot of risks with the software your team started testing activities early by overseeing code reviews, defining acceptance criteria by working with the users and by doing all lest creation prior to the code arriving.

You are now three days away from the go-live date.

Your testing has mitigated all the high and medium risk items leaving only the low-risk elements unmitigated by testing.

You estimate it will take two weeks to manually test the low-risk elements.

At this point what should you do?

  1. A

    Automate the testing of the untested elements to ensure they are covered

  2. B

    Block the go-live and start testing the low-risk elements immediately

  3. C

    Transfer the risk of the untested low-risk items to the help desk

  4. D

    Select one of the low-risk elements and perform depth testing to assess the residual risk

Show answer and explanation

Correct answer: D

Explanation

Context Analysis:
With limited time, testing all low-risk elements is not feasible. Depth testing on a representative low-risk element helps assess potential residual risk efficiently.
Evaluation of Options:
A. Automate the testing of the untested elements to ensure they are covered:
Incorrect. There isn't enough time to implement automation.
B. Block the go-live and start testing the low-risk elements immediately:
Incorrect. Blocking the release may not be acceptable if high and medium risks are already mitigated.
C. Transfer the risk of the untested low-risk items to the help desk:
Incorrect. While a potential fallback, it doesn't address residual risk proactively.
D. Select one of the low-risk elements and perform depth testing to assess the residual risk:
Correct. This provides quick insights into potential risks and helps make an informed go/no-go decision.
Syllabus Alignment:
ISTQB emphasizes prioritizing risk mitigation through targeted testing (TM-1.3.4).
References:
ISTQB Advanced Level Test Management Syllabus (TM-1.3.4)

Question 8 Single choice

Which of the following is the proper order for the stages of a tool lifecycle?

  1. A

    Acquisition Support Evolution Retirement

  2. B

    Acquisition Evolution Support Retirement

  3. C

    Evolution Acquisition Retirement Support

  4. D

    Evolution Support Acquisition Retirement

Show answer and explanation

Correct answer: A

Explanation

Definition of Tool Lifecycle Stages: Acquisition:The tool is selected and procured.
Support:Maintenance and updates are provided to ensure ongoing usability.
Evolution:The tool is upgraded or adapted for new needs.
Retirement:The tool is decommissioned when no longer useful.

Evaluation of Options:
A. Acquisition Support Evolution Retirement:
Correct. This sequence reflects the natural progression of a tool lifecycle.
B. Acquisition Evolution Support Retirement:
Incorrect. Support should occur before evolution as maintenance ensures stability before upgrades.
C. Evolution Acquisition Retirement Support:
Incorrect. Evolution cannot occur before acquisition.
D. Evolution Support Acquisition Retirement:
Incorrect. Acquisition must come first.
Syllabus Alignment:
ISTQB highlights the lifecycle stages of tools in test environments as starting with acquisition and ending with retirement (TM-1.6.4).
References:
ISTQB Advanced Level Test Management Syllabus (TM-1.6.4)

Question 9 Single choice

You are the Test Manager for a project for a new entertainment booking system using Agile. The project's objectives include:

Online response time must satisfy customers Payments must be secure against fraud
In case of system failure, only transactions in progress can be lost Which option meets all the criteria of the S.M.A.R.T.
goal methodology?

  1. A

    All system and acceptance tests on all new features will be automated for regression testing

  2. B

    Regular performance efficiency testing will be carried out by specialist performance testers

  3. C

    Each release will receive security testing by external specialists for known vulnerabilities

  4. D

    Each iteration will receive reliability testing to show that only transactions in progress are lost

Show answer and explanation

Correct answer: D

Explanation

This test objective is: Specific: Reliability testing for transaction safety Measurable: Validate loss only for in-progress transactions Achievable: Done per iteration Relevant: Directly relates to a system failure objective Timely: Per iteration (i.e., bounded in time)
"SMART" goals are Specific, Measurable, Achievable, Relevant, and Time-bound. A good test objective supports stakeholders' need for informed decisions on system readiness.

Question 10 Single choice

Which of the following are Test Closure activities? SELECT ONE OPTION

a- All results lodged in configuration management system - for example test plans, results, logs, reports. b- Plans in place for lessons to be learnt to ensure that good practices are repeated and poor practices are not. c- Checks undertaken to ensure that all test work is completed - all tests executed or skipped, all defects managed to appropriate conclusion. d- All project closure activities completed - for example customer training completed, and analysis of vendor performance undertaken. e- AM testing work products delivered to those that need them - for example environments/ regression test sets passed to maintenance. f- Checks undertaken to ensure that all tests have been executed, with all defects confirmed as fixed by retesting.

  1. A

    a, c, d and f.

  2. B

    a, b, c and e

  3. C

    a.b, e and f.

  4. D

    b, c. d and e.

Show answer and explanation

Correct answer: B