A good MRP system generates exception messages:
A. To advise the planner when some event needs attention
B. When the manufacturing process is under control
C. When there are problems that need the attention of the planner
D. Both A and C
Which of the following situation that will leads or generates Exception messages?
A. Components for which planned orders are in the action bucket and which should be considered for release
B. Open orders for which the timing or quantity of scheduled receipts does not satisfy the plan.
C. Situations in which the standard lead times will result in late delivery of a Zero-level part
D. All of the above
The orders are automatically scheduled and controlled by the computer are the orders called:
A. Planned orders
B. Computer generated order
C. Firms planned order
D. All of the Above
The material planner works with the type of orders
A. Four
B. Three
C. Seven
D. Two
The process of colleting the gross requirements and netting can be simplified by using
A. Low-level codes
B. Planning horizon
C. Time buckets
D. Action buckets
Which of the following details are true about time buckets EXCEPT:
A. These are often a week
B. Can be any length of time convenient to the company
C. Companies can move to daily time buckets
D. Needs to avoid future problems
At the MRP planning level, the process of priority plans must be checked against available capacity is called
A. Master Production schedule (MPS)
B. Capacity Requirements planning (CRP)
C. Production activity control (PAC)
D. Manufacturing Planning and control function (MPC)
Planning horizon means
A. The number of periods in the record
B. The most current period in the record
C. The quantity of the records
D. None of the above
Scheduled receipts shows:
A. The quantities ordered
B. When quantities ordered are expected to be completed
C. When quantities ordered are expected to be available
D. All of the Above
The immediate or most current period is called
A. Action bucket
B. Planning horizon
C. Time buckets
D. Both a and B
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APICS exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CPIM-MPR exam preparations and APICS certification application, do not hesitate to visit our Vcedump.com to find your solutions here.