Question 1 Single choice

This figure is a true representation of:

  1. A

    MRP II

  2. B

    MPS

  3. C

    Production Plan

  4. D

    None of these

Show answer and explanation

Correct answer: A

Question 2 Single choice

When there is uncertainty in the supply chain based on the use of forecasts, and that uncertainty is then exaggerated by lead-time effects and differences in lot sizes as material moves through the supply chain, this is called:

  1. A

    Bullwhip effect

  2. B

    Anticipatory effect

  3. C

    Bull ship effect

  4. D

    None of the above

Show answer and explanation

Correct answer: A

Question 3 Single choice

exists when the cumulative actual demand varies from the cumulative forecast.

  1. A

    Bias

  2. B

    seasonal index

  3. C

    Actual forecast

  4. D

    Stable demand

Show answer and explanation

Correct answer: A

Question 4 Single choice

describes the function of the organization.

  1. A

    Vision statement

  2. B

    Mission statement

  3. C

    Policy statement

  4. D

    Service statement

Show answer and explanation

Correct answer: B

Question 5 Single choice

What have most of the values clustered near a central point with progressively fewer results occurring away from the cluster?

  1. A

    Normal distribution

  2. B

    Frequent distribution

  3. C

    Average distribution

  4. D

    Relevant distribution

Show answer and explanation

Correct answer: A

Question 6 Single choice

Independent demand is:

  1. A

    Directly related to the demand for any other products or assemblies

  2. B

    Not related to the demand for any other products or assemblies

  3. C

    Calculated

  4. D

    A & C

Show answer and explanation

Correct answer: B

Question 7 Single choice

____________________ are concerned with the end use of the item and what the item is expected to do.

  1. A

    Functional specifications

  2. B

    Price requirements

  3. C

    Quality assurance

  4. D

    Performance requisition

Show answer and explanation

Correct answer: A

Question 8 Single choice

The time needed to unload and load must be shorter than .

  1. A

    run time per piece

  2. B

    planning time

  3. C

    manufacturing time

  4. D

    resource utilization time

Show answer and explanation

Correct answer: A

Question 9 Single choice

shows the quantities needed and when manufacturing intends to make use or use them.

  1. A

    MPS

  2. B

    Production plan

  3. C

    Purchasing and production activity control

  4. D

    Material Requirement Plan

Show answer and explanation

Correct answer: D

Question 10 Single choice

Which one of following is not an important factor in supply chain?

  1. A

    The supply chain includes all activities and processes to supply a product or service to a final customer

  2. B

    Any number of companies can be linked in the supply chain

  3. C

    product or services usually flow from customer to supplier and design and demand information usually flows from customer to supplier. Rarely is this not so.

  4. D

    A customer can be a supplier to another customer so the total chain can have a number of supplier customer relationships.

Show answer and explanation

Correct answer: C