Question 1 Single choice

The group whose remit is to set the strategic direction of a project is commonly known as:

  1. A

    the project management team.

  2. B

    primary user group.

  3. C

    steering group.

  4. D

    supplier group.

Show answer and explanation

Correct answer: C

Question 2 Single choice

A review undertaken to decide whether a project should proceed into its next phase is known as a...

  1. A

    decision gate.

  2. B

    feasibility study.

  3. C

    milestone review.

  4. D

    evaluation review.

Show answer and explanation

Correct answer: A

Question 3 Single choice

How can the project manager ensure a sound stakeholder environment?

  1. A

    Ensure that stakeholders who oppose the project are not involved

  2. B

    Develop an environment where all stakeholder's needs are satisfied.

  3. C

    Develop ways of understanding the needs of stakeholders.

  4. D

    Ensure that the influence stakeholders have is reduced.

Show answer and explanation

Correct answer: C

Question 4 Single choice

One benefit of stakeholder analysis is that:

  1. A

    the communication plan becomes unnecessary.

  2. B

    the stakeholders who oppose the project the most can be "cut off' to reduce their negative influence.

  3. C

    the communication requirements for each stakeholder Can be established.

  4. D

    the stakeholders can be removed from any of the decisions that are bang planned.

Show answer and explanation

Correct answer: C

Question 5 Single choice

Quality control verifies that:

  1. A

    the project follows appropriate processes.

  2. B

    project outputs are delivered on time.

  3. C

    the project follows appropriate governance.

  4. D

    project outputs meet acceptance criteria.

Show answer and explanation

Correct answer: D

Question 6 Single choice

As part of the risk management process the capture of threats and opportunities to the project objectives are referred to as:

  1. A

    risk assessment.

  2. B

    risk avoidance.

  3. C

    risk exposure.

  4. D

    risk identification.

Show answer and explanation

Correct answer: D

Question 7 Single choice

Which of these is a correct definition of an Estimate?

  1. A

    The use of a range of tools and techniques to produce forecasts of the probable time or cost of completing work

  2. B

    An educated guess that improves over time

  3. C

    A forecast of the probable time or cost of completing work

  4. D

    An estimate is an approximation of project time and cost targets that forms the basis of the contract

Show answer and explanation

Correct answer: C

Question 8 Single choice

What aspects of benefits realisation would be considered as most important to note in the business case?

  1. A

    Who is going to be responsible for carrying out each of the projects activities.

  2. B

    How the benefits will be realised, measured and the stakeholders involved

  3. C

    What type of contract is going to be used to procure delivery of the project.

  4. D

    Which benefits should be realised first and then the subsequent order

Show answer and explanation

Correct answer: B

Question 9 Single choice

One way that communication could be improved in the project is to:

  1. A

    ensure that free flowing feedback channels are planned into the communication structure.

  2. B

    ensure that communication is carried out as much as possible, transmitting as much information as possible.

  3. C

    target only those stakeholders who seem to show a valid interest in the project.

  4. D

    avoid planning communication too much so that messages are not seen as rigid and overly complex.

Show answer and explanation

Correct answer: A

Question 10 Single choice

The prime purpose of configuration management is to:

  1. A

    ensure the traceability and integrity of the delivered product or products

  2. B

    minimise the impact of changes on the scope of the project

  3. C

    ensure that the final product meets the needs of the business as defined by key stakeholders.

  4. D

    maximise the impact of agreed enhancements to the project deliverables

Show answer and explanation

Correct answer: A