APM APM-PFQ Online Questions & Answers

  • Question 341:

    What might be considered a disadvantage of virtual communication?

    A. Digital communication links never seem to work as required.
    B. Communication being misunderstood.
    C. There is no method for providing feedback.
    D. This method of communication tends to be time consuming.

  • Question 342:

    What is one of the main features of using analogous method of estimating?

    A. The individual group members use a statistical relationship between historic data and other variables to calculate an estimate.
    B. The task of producing the estimates will be delegated to those who are actually going to deliver the individual pieces of work or work packages.
    C. The individual group members, who are tasked with providing the estimates, do this in isolation from each other.
    D. The individual group members identify a previously delivered project of the same size. complexity and delivery method.

  • Question 343:

    A formally constituted group of stakeholders responsible for approving or rejecting changes to the project baselines, is referred to as the:

    A. change management committee,
    B. change authority,
    C. change control board.
    D. change implementation group.

  • Question 344:

    The role of a leader includes:

    A. effectively managing risks.
    B. selecting the project team.
    C. coaching and mentoring project staff.
    D. producing accurate project reports.

  • Question 345:

    One purpose of risk management is to:

    A. adapt the plan to resolve problems.
    B. minimise threats and maximise opportunities.
    C. continually improve the project teams' efficiency.
    D. manage variations in a controlled way

  • Question 346:

    What is a visual representation of a project's planned activity against a calendar called?

    A. A Gantt chart.
    B. A critical path network.
    C. A product flow diagram.
    D. A Pareto chart.

  • Question 347:

    A review most closely linked to the phases Of the project life cycle could be described as a:

    A. gate review.
    B. learning review.
    C. handover review.
    D. audit review.

  • Question 348:

    We have an expert-written solution to this problem. Who has ultimate responsibility for project risk?

    A. Steering group.
    B. Risk owner.
    C. Project sponsor.
    D. Project manager

  • Question 349:

    Estimating by using historical information is known as:

    A. comparative estimating.
    B. parametric estimating.
    C. bottom-up estimating.
    D. strategic estimating.

  • Question 350:

    One way that communication could be improved in the project is to:

    A. ensure that free flowing feedback channels are planned into the communication structure.
    B. ensure that communication is carried out as much as possible, transmitting as much information as possible.
    C. target only those stakeholders who seem to show a valid interest in the project.
    D. avoid planning communication too much so that messages are not seen as rigid and overly complex.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-PFQ exam preparations and APM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.