Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?

In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
A. The delay must affect the critical path.Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

What activities are concurrent to Activity 2001 in the "normal" schedule?

What owner action could have mitigated the late completion of the project?
A. Hire a more senior project manager.What is the result of a forward pass calculation?
A. Value of total float for individual activitiesFree float is the
A. Difference between the early dates and late dates of an activity.An earned value-based project control system can use either of which two budgets as the basis of its calculations?
A. Labor hours or dollars.Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
A. Multiple calendars.If all other work proceeds according to the Baseline plan, how many times will the critical path change?

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only AACE International exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your AACE-PSP exam preparations and AACE International certification application, do not hesitate to visit our Vcedump.com to find your solutions here.