Which of the following are NOT considerations or constraints of the planning process for construction scheduling?
A. Consideration of all stakeholders.What is the actual duration as of the status date or data date of Activity B?

A driving relationship is _____________________.
A. A critical relationship.Total float is defined as the amount of time an activity can be delayed without impacting
A. The overall project completionIn its simplest form, what is the main drawback of critical path method scheduling?
A. It requires a backward pass to calculate late dates.The activity with the most total float is:

What is the free float for Activity F?

If no time extensions are granted and all actual delays are as described above, what will the total float calculation be at the end of the project?
A. 0 calendar days.Which of the following project planning situations is the most frequent contributor to cost overruns?
A. lack of detailed planning for operational start-upWhat is a key first step in developing a critical path method schedule?
A. Drawing a bar chart of the key phrases of the work.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only AACE International exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your AACE-PSP exam preparations and AACE International certification application, do not hesitate to visit our Vcedump.com to find your solutions here.