AACE-PSP Exam Details

  • Exam Code
    :AACE-PSP
  • Exam Name
    :Planning & Scheduling Professional (PSP)
  • Certification
    :AACE International Certifications
  • Vendor
    :AACE International
  • Total Questions
    :120 Q&As
  • Last Updated
    :Jul 13, 2026

AACE International AACE-PSP Online Questions & Answers

  • Question 91:

    Which statement is true?

    A. Where compensability cannot be established, excusability is assumed.
    B. Where compensability can be established, excusabltity cannot be assumed.
    C. Where compensability cannot be established, excusability is a given.
    D. Where compensability can be established, excusability is assumed.

  • Question 92:

    If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

    A. 15 days.
    B. 10 days.
    C. 0 days.
    D. 5 days.

  • Question 93:

    Determine the driving activity for Activity 10001.

    A. Activity 11001.
    B. Activity 10002.
    C. Activity 9005.
    D. There is no driving activity for Activity 10001 in the backward pass.

  • Question 94:

    Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

    A. 3.9% (1 : 25.708)
    B. 2.3% (1 : 43.501).
    C. 9.1% (1 : 11.000).
    D. 8.6% (1 : 11.591)

  • Question 95:

    Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003.

    What is the duration of the hammock?

    A. 407 days
    B. 362 days
    C. 255 days
    D. 267 days

  • Question 96:

    Determine the correct formula and date for the late finish for Activity 9004.

    A. LS.10002 + 1 day -> 11-29-03.
    B. LS.10002^ Lag.7 + i day -> 11-20-03.
    C. LS.10002 - 1 day -> 11-27-03.
    D. LS.10002 - Lag.7 - l day -> 11-20-03.

  • Question 97:

    For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

    A. LS.11001 + 25 days.
    B. 02-19-04.
    C. EF.11001.
    D. EF.11001 + 1 day.

  • Question 98:

    At the end of month one, did the delay to the parking structure foundation delay the project?

    A. NO.
    B. Yes, by 4 calendar days.
    C. Yes, by 14 calendar days.
    D. Yes, by 9 calendar days.

  • Question 99:

    Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

    A. 15 days.
    B. 0 days.
    C. 5 days.
    D. 10 days.

  • Question 100:

    Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

    A. C.
    B. B.
    C. S.
    D. W.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only AACE International exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your AACE-PSP exam preparations and AACE International certification application, do not hesitate to visit our Vcedump.com to find your solutions here.