If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?
A. 15 days.
B. 10 days.
C. 0 days.
D. 5 days.
Which of the following is NOT required when initially planning a project?
A. Resource Identification and leveling.
B. The duration of each task.
C. A schedule that identifies tasks required on a project.
D. Logical relationships between the tasks.
At the end of month one, did the delay to the parking structure foundation delay the project?
A. NO.
B. Yes, by 4 calendar days.
C. Yes, by 14 calendar days.
D. Yes, by 9 calendar days.
Budgeted cost of work scheduled is _______________________.
A. The value of the completed work expressed in terms of the budget assigned to that work
B. The total authorized budget for accomplishing the project scope
C. The expected total cost of an activity, group of activities or the project
D. The sum of all budgets for work scheduled to be accomplished within a given time period
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
A. 407 days
B. 362 days
C. 255 days
D. 267 days
You are retained by a contractor who asks you to perform a simple as-planned versus as- built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
A. Not suitable for complicated projects with multiple planned critical paths.
B. Accuracy is increased by inserting delaying events into the as-planned schedule.
C. Not suitable for projects with long durations.
D. Less accurate as the analysis advances through the project.
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?
A. Delay product release by 5 days.
B. Expedite packaging by 5 days.
C. Expedite printing by 5 days.
D. Delay manufacturing by 5 days.
How much Total Float does drafting the product manual have?
A. 15 workdays.
B. 0 workdays.
C. 10 workdays.
D. 5 workdays.
Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?
A. $271,000
B. $299,000
C. $139,000
D. $289,000
If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?
A. The Eichleay formula
B. Historical production rates
C. Time impact analysis
D. Black-Scholes model
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only AACE International exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your AACE-PSP exam preparations and AACE International certification application, do not hesitate to visit our Vcedump.com to find your solutions here.