Exam Details

  • Exam Code
    :AACE-PSP
  • Exam Name
    :Planning & Scheduling Professional (PSP)
  • Certification
    :AACE International Certifications
  • Vendor
    :AACE International
  • Total Questions
    :163 Q&As
  • Last Updated
    :Jun 25, 2025

AACE International AACE International Certifications AACE-PSP Questions & Answers

  • Question 101:

    Which of the following will always describe the critical path? The path with

    A. The longest duration through the network.

    B. Zero float.

    C. Negative float.

    D. The shortest duration and negative float.

  • Question 102:

    Determine the correct formula and date for the late start for Activity 9001.

    A. The early finish is required in order to determine the answer.

    B. LS.6001 Dur.6001 -> 11-20-02.

    C. There is insufficient data provided to calculate the answer.

    D. LF.9001 Dur.9001 -> 11-20-02.

  • Question 103:

    What is the workweek period for this project?

    A. Monday through Friday

    B. Sunday through Friday

    C. Monday through Saturday

    D. Sunday through Saturday

  • Question 104:

    Each of the following accurately describes total float in a schedule EXCEPT:

    A. The amount of time an activity can be delayed without delaying the overall project completion time.

    B. Can be positive or negative.

    C. The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.

    D. Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.

  • Question 105:

    What activities are concurrent to Activity 2001 in the "normal" schedule?

    A. 7001.

    B. 1001.

    C. 1000.

    D. 2003.

  • Question 106:

    If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

    A. Is a milestone.

    B. It is on the critical path.

    C. Was completed in the past.

    D. Has yet to be completed.

  • Question 107:

    Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

    A. 15 days.

    B. 0 days.

    C. 5 days.

    D. 10 days.

  • Question 108:

    By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:

    A. Acceleration.

    B. Production output.

    C. Productivity loss.

    D. Productivity efficiency.

  • Question 109:

    Determine the correct formula and date for the late finish for Activity 2002.

    A. LS.2003 - 1 day -> 11.06.01.

    B. LS.2003 - 1 day -> 10-06-01.

    C. LS.2003 + 1 day -> 10-07-01.

    D. LS.2003 - 1 day -> 10-05-01.

  • Question 110:

    What is a key first step in developing a critical path method schedule?

    A. Drawing a bar chart of the key phrases of the work.

    B. Defining the execution plan to meet the required scope of work.

    C. Setting out the resource to be used and its limitations.

    D. Drawing the logic diagram.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only AACE International exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your AACE-PSP exam preparations and AACE International certification application, do not hesitate to visit our Vcedump.com to find your solutions here.