You are the business analyst for your organization and you've been working with several stakeholders to gather requirements for approval.
The requirements have been approved with the exception of a conflict on one requirement. What must you and the stakeholders do in regard to this conflict before the business analysis endeavor may continue?
A. The requirement with the conflict should be excluded from the approved set of requirements and must be resolved before it can be joined to the approved set of requirements.
B. The conflict must be documented as a risk.
C. The conflict must be resolved before the set of requirements may be approved.
D. The conflict must be documented in an issues log, assigned to an issue owner, and then the endeavor may continue.
A finance manager wants to begin a new project to replace the existing expenses processing system. The finance manager feels that the current expense submission-to- reimbursement process takes too long and is substantiated by 50% more complaints regarding incorrect reimbursement amounts than the same time last year. What should the business analyst (BA) investigate first?
A. Submission processes to determine which activities can be fully automated
B. Business process to uncover inefficiencies and falling control points
C. Enterprise information model to ensure definitions are still valid
D. Finance solution vendors for inclusion in a Request for information
A software company wants to make a gradual change from its traditional way of developing requirements to a more adaptive approach. A business analyst (BA) is hired to quantify the probability that the solution will meet the company's needs and assess the relevant risks. Which element of risk assessment does the BA need to consider?
A. Negative Impact to value
B. Positive Evaluation Results
C. Risk Tolerance
D. Issue Management
Which of the following documents graphically depicts the project team members and displays their interrelationship for a specific project?
A. Project team directory
B. Project organization chart
C. Project scope statement
D. Project charter
The project plan called for deliverables to be handed over at the end of the project. Although the client's business team was satisfied, the client's technical team was extremely resistant to this approach. What could the business analyst (BA) do to mitigate the technical team's resistance?
A. Escalate to project sponsor
B. Meet with technical team
C. Reassess the project objectives
D. Email the business team
A business. analyst (BA) is working on a project to implement a commercial off-the-shelf application for tracking customers. In an observation session with a Domain subject matter expert (SMF). the BA notes that the SME keeps separate records for the customers who are also vendors. The BA knows that the new software has a module for vendor management that would integrate the vendor and customer records. Which type of opportunity has the BA identified?
A. Reduction of duplicate tasks performed by staff
B. Potential to provide future value supported by the system
C. Ability to provide greater amount of information to staff
D. Automation to increase consistency of behavior
A business analyst (BA) is informing stakeholders about the importance of quality when eliciting requirements. What characteristic describes a quality requirement?
A. Simplistic
B. Consistent
C. Critical
D. Functional
A business analyst (BA) working with a large insurance corporation interviewed an industry thought leader who predicted that many of the regulations currently imposed by the government will change very soon. The BA communicated the observation to the leadership team of the organization because many on-going projects were triggered by those regulations. The leadership team unanimously decided to cancel the initiatives that were driven by the government regulations. What is the corporation's attitude towards risk?
A. Risk Neutral
B. Risk Averse
C. Risk Tolerant
D. Risk Seeking
A business analyst (BA) has developed requirements for a project containing sensitive information. The requirements were approved and the solution was implemented. What should the BA do to ensure these requirements are maintained for future reference?
A. Print the requirements package and distribute it to stakeholders in person
B. Archive the requirements package in the business analysis portal
C. Store the requirements package on secure shared drive
D. Send the requirements package to stakeholder in a password protected email
A business analyst (BA) is preparing the elicitation activity plan for a project. How will understanding the elicitation scope assist the BA with the elicitation activity?
A. By ensuring the requirements are validated in time
B. By demonstrating how to record elicitation results
C. By outlining the level of stakeholder collaboration
D. By determining when elicitation is complete
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IIBA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CCBA exam preparations and IIBA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.