You are a project manager in an organization that uses Microsoft Project.
You are managing a project, which involves the construction of a new shopping mall. The shopping mall is scheduled to finish by October 21. The mall needs to start operations by October 31. Your sponsor asks you to closely monitor your
schedule and informs you that missing the October 21 deadline could jeopardize the October 31 start date.
You are concerned about construction delays, and you want to reduce the time buffer. Your sponsor agrees with this decision.
You need to show the time between the End of Construction and the Grand Opening Day as a time buffer for delays.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A. Create a deadline for the Grand Opening Day task on October 31.A company is open for business Monday through Friday, 7:30 A.M. to 4:30 P.M. The company closes a total of eight full days and two half days for holidays each year. For the months of June, July, and August, the company closes at 1 P.M.
on Fridays.
You need to ensure that all projects show when employees can perform work.
Which three actions should you perform? Each correct answer presents part of the solution.
A. Edit the standard calendar.Your organization uses Microsoft Project and records actual hours worked on the project.
You manage a small e-commerce website implementation project. One of your testers asks for assistance in completing a critical task, and you find two additional testing resources that can assist with executing the critical test cases.
The total estimated work for the effort-driven task is 100 hours. The original testing resource, Resource1, completes 25 hours of work on the task.
You need to add Resource2 and Resource3 to the task and split the remaining hours across all three resources now working on the task.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A. Open the Task Form and format it to show Work Details. Enter 25 hours of actual work for Resource1. Then save the changes.You are a project manager who uses Microsoft Project.
You work on a project that requires you to generate many documents. Each task in your project plan must have a document associated and stored in your Microsoft SharePoint Intranet Environment. These documents are 25 megabytes in
size.
You need to share this project plan by email with your team and ensure that they can easily access the documents.
What should you do?
A. In the Task Information notes, insert an object from a file. Uncheck the Link option and make sure that it is a document, not a link. Select your document and click on it. Project will automatically create the reference to this document.Your organization uses Microsoft Project.
A senior stakeholder informs you that your project start date is delayed and gives you a new start date.
You need to change the project start date without adding constraints.
What are three possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose three.)
A. Modify the Start Date field in project information to the new date.Your company uses Microsoft Project to track project progress.
You need to accurately calculate cost performance index (CPI) as a health indicator.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
A. Ensure there is a value in the Status Date field.You are a project manager who uses Microsoft Project.
You manage a critical project, which involves many team members. You are the only team member who has Microsoft Project. You need to receive updates from team members directly from Microsoft SharePoint without having to reenter the
updates in your project.
What should you do?
A. Set up your project to sync with a SharePoint Task List.You are evaluating a completed project by using Microsoft PPM.
You have displayed the Resource Sheet view and selected the Work table. In this project, the Custom Service Team was responsible for 25 tasks.

Use the drop-down menus to select the answer choice that answer each question.
Hot Area:

You are a project manager, and your company uses Microsoft Project. You are setting up a preliminary schedule by using manually scheduled tasks.
You create two manually scheduled tasks and link them in a Finish to Start relationship. The project team member asks you to increase the duration of the predecessor task.
You notice that the successor task start date is now before the finish date of the predecessor task.
You want the successor task to start after the predecessor finishes.
What should you do?
A. Select both tasks and click Unlink.You use Microsoft Project to manage a project that has customer-required milestone completion dates. You need to see graphically that your milestones have slipped beyond your customer-required dates. What should you add to the project milestones?
A. a Must finish on constraintNowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 74-343 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.