You are a project manager for a company that uses Microsoft Project.
You are developing a schedule and plan to use the leveling order of Priority, Standard.
You need to create a task which leveling will not change.
What should you do?
A. Set task priority to 100You recently updated a schedule by using Microsoft Project.
The vice president of engineering has asked you to show progress only on project milestones and identify milestones falling behind.
You need to find a way to show milestone progress.
Which solution would you meet this objective?
A. Run the Late Tasks report.You are a project manager who uses Microsoft Excel.
Your company decides to migrate all of the current projects in Microsoft Excel to Microsoft Project. They allow all employees to spend 8 hours migrating each project plan. Your current and unique project plan has 462 tasks with duration in
days, and resources have been assigned and named. You have a status meeting in two days.
You need to provide your project's information by using Microsoft Project.
What should you do?
A. Create a new project plan in Microsoft Project and use the Gantt Chart Wizard to import from an Excel Workbook.You are a project manager, and you successfully complete a server consolidation project for one of your data centers. You use Microsoft Project to plan and track the work.
Your manager wants you to begin similar projects on two other data centers. You need to create a template based on the plan you used to manage the first data center consolidation project.
You need to ensure that the template has all baseline and actual data values removed.
What should you do?
A. Within Microsoft Windows Explorer, create a copy of the original project plan and rename the file type from .mpp to .mpt.Your company uses Microsoft Project.
You are setting up a preliminary schedule by using manually scheduled tasks. You create a task with no duration, start, or finish date, and then you assign a resource. Later, you enter a duration of three days for that task.
You need to let the resource know how the Work will be affected.
What should you say?
A. Work will increase to 24 hours.Your company uses Project Professional 2013.
You are a program manager in charge of a multi-program software integration project. The project is scheduled from January 1, 2012-August 3, 2013. You have a consultant resource that charges a different rate based on each task
completed. Tasks 1 through 9 are billed at a rate of $150.00 per hour. Tasks 10 through 20 are billed at a rate of $175.00 per hour. You need to set up your schedule to ensure that the correct resource rate is associated with the correct tasks.
Which two actions should you perform in sequence? (To answer, move the appropriate two actions from the list of actions to the answer area and arrange them in the correct order.)
Select and Place:

Your organization uses Microsoft Project.
You are setting up a preliminary schedule by using manually scheduled tasks.
As you build the task breakdown, you notice a potential scheduling problem indicated by a wavy red line under the finish date of a detail task.
You need to determine the cause of the wavy red line.
What should you do?
A. Evaluate the task to determine if there is a deadline.You are tracking a project schedule by using Microsoft Project. The project schedule contains a baseline.
You need to display a view that displays the slippage of the current plan as compared to the baseline for the schedule.
Which two actions will achieve the goal? Each correct answer presents a complete solution.
A. Display the Leveling Gantt and format the chart to display the current plan schedule.You create a new project by using Microsoft Project. You have a list of tasks and a list of resources. All tasks are manually scheduled.
You need to determine which action you can perform by using the Team Planner view.
Which actions can you perform?
A. You can move a task to the Unassigned Tasks pane, and work associated with the task is saved.You manage a project schedule by using Microsoft Project.
You are concerned about project costs. After viewing the Cost Variance column, you realize that the project has a cost variance of 55,000.00.
You need to view graphically which tasks and resources are causing the $5,000.00 cost variance.
What should you do?
A. View the Resource Graph's Cumulative Cost view.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 74-343 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.