Q94 Single choice

A project manager is working with several junior engineers on a project. The project manager noticed that when the junior engineers are asked questions, they defer te more senior team members on the team for answers. Having worked with the junior engineers on another project, the project manager knows they are capable of making these minor decisions correctly. This uncertainty from the junior engineers is now slowing progress.

What should the project manager do?