Q25 Multiple choice

A project for developing software for a retail company's procurement system is in the initiation phase. The project sponsor has expressed concern that the forecasted project implementation date coincides with the
company's financial budget planning period.

Which two actions should the project manager take next to address this concern? (Choose two.)

Select all that apply.