Q35 Single choice

A project team has installed software for the client, passed the knowledge to operations, sent the final report, and celebrated. Then 1 week later, the client sendsa list of requirements that have not been met.
The client is requesting to fix the issues quickly and within the initial budget.

What should the project manager have done to prevent this from happening?