Question 53 of 100
0% complete
Q53 Single choice

A team member is frustrated, thinking that their performance is below average since they have not completed as many items as other team members. The team member has become negative and disengaged, bringing team collaboration and productivity down.

What should the project manager do to increase the team's performance?