A CEO asks the Development Team to add a new item to the Sprint. What should the Development Team do in response?
A. Refer it to the Product OwnerWhich of the following about User Story Acceptance Criteria is true?
A. User Stories are objective, and the Acceptance Criteria provides the subjectivity required for the User Story to be considered as Done.A project on developing quality testing equipment for an agro-based industry will start with the Create Deliverables process. Which of the following are NOT inputs to the current process?
A. Scrum Core TeamYou are the Scrum Master for your organization and you're training the Product Owner and the Development Team on the rules of Scrum. After a few Sprints in the project, the Development Team is getting used to processes and flow of the work. With their confidence, the Development Team has decided that a Sprint Retrospective is no longer needed in the project. What should you do regarding the team's desire to no longer have a Sprint Retrospective?
A. You should demand the Development Team host a retrospective as it is a rule of Scrum.The Scrum framework, being an Agile iterative process, inherently minimizes risk. Many Scrum practices facilitate effective management of risk. Choose the option that is NOT a correct pairing of a Scrum characteristic with its role in minimizing risk:
A. Flexibility: Business-environment-related riskYou are the Scrum Master for an organization which is new to Scrum practices. The Development Team is having trouble understanding the concept of a self-organizing Development Team. Which one of the following statements best describes the concept of a self-organizing team?
A. A self-organizing team determines the best approach to reach the definition of done.A new developer is having continuing conflicts with existing Development Team members and creating a hostile environment. If necessary, who is responsible for removing the team member?
A. The organization's management is responsible for managing unruly Development Team members.Which one of the following is NOT a type of identified dependencies in a Scrum project?
A. CriticalScrum Master is the 'servant leader' of Scrum Team. In this context, which of the following is a key responsibility of the Scrum Master?
A. Help create Project Vision StatementWhich of the following meetings is not usually Time-boxed?
A. Daily Standup.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Scrum exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your SCRUM-SMC exam preparations and Scrum certification application, do not hesitate to visit our Vcedump.com to find your solutions here.