  • Question 91:

    You're working with the Product Owner and the Development Team to create a Sprint burndown chart. The Product Owner doesn't see the value in the Sprint burndown chart. What's the value of the Development Team creating this chart?

    A. A sprint burndown chart will show which Development Team members are getting.
    B. A sprint burndown chart will show an estimate of the work remaining for the Sprint.
    C. A sprint burndown chart will show how long a Sprint will be.
    D. A sprint burndown chart will show the duration of each user story in a Sprint.

  • Question 92:

    You are the Scrum Master on a project that is reconstructing the drinking water and sewage system of the city of BogotA. Which of the following characteristics do you NOT need to be?

    A) Persuasive B) Discerning C) Intuitive D) Visionary

    A. A, C, and D
    B. A and D
    C. All of the above.
    D. None of the above.

  • Question 93:

    Which one of the following is an output of Sprint Planning and is used to give the Development Team a Sprint target?

    A. Sprint Goal
    B. Roles and Responsibilities
    C. Product Backlog
    D. Team charter

  • Question 94:

    Gary, a Development Team member, wants to know how long a Daily Scrum is. What's the timebox for a Daily Scrum?

    A. 4 hours or less
    B. 15 minutes
    C. 2 hours
    D. 1 hour

  • Question 95:

    Which of the following best defines the team velocity metric used to measure team performance?

    A. Team velocity is the total number of hours the team has worked during a Sprint.
    B. Team velocity is the total number of story points completed in a given Sprint.
    C. Team velocity is the percentage of story points that have been Done versus those committed.
    D. Team velocity is the actual time spent on delivering User Stories.

  • Question 96:

    Mark is the Product Owner and he asks you, the Scrum Master what burndown charts actually track. What's the best response for Mark?

    A. Burndown charts will track the remaining work across the project time.
    B. Burndown charts will track the value of the work performed by the Development Team.
    C. Burndown charts will track work still left in the project.
    D. Burndown charts will track the cost of the work.

  • Question 97:

    You are the Scrum Master for the ID7 Project for your organization. Martha is serving as the Product Owner for this project. Martha meets with you and asks for your advice on how she should go about estimating the work in the Product Backlog. What should you tell Martha?

    A. The Development Team will work with Martha to estimate the items in the Product Backlog with story points.
    B. The Development Team will work with you, the Scrum Master, to create time and cost estimates for all the Product Backlog items.
    C. Martha can estimate the items in the Product Backlog, but you, the Scrum Master, must be approve the estimates prior to each Sprint Planning meeting.
    D. Martha can estimate the items in the Product Backlog, but the Development Team must approve the estimates prior to the Sprint beginning.

  • Question 98:

    Scrum is_____________________

    A. A framework to address complex adaptive problems
    B. A collection of the industry's best practices in information technology
    C. A body of knowledge on software engineering to build products

  • Question 99:

    Which of the following events does NOT help the Scrum Team in identifying or resolving risks?

    A. Daily Standup Meeting
    B. Sprint Planning Meeting
    C. Financial Planning Meeting
    D. Prioritized Product Backlog Review Meeting

  • Question 100:

    A large software company has 8 Scrum teams with each team having a Scrum Master. After the Daily Standup everyday with their respective teams, all Scrum Masters meet for a Scrum of Scrums. What are they likely to do during this meeting?

    A. Discuss ways to resolve technical impediments faced by development teams, especially if two or more teams face the same issue.
    B. Discuss what each individual development team member has worked on since the last time all Scrum Masters met.
    C. Discuss actions of a team that could potentially affect another team.
    D. Share a status update on all individual team member' tasks.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Scrum exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your SCRUM-SMC exam preparations and Scrum certification application, do not hesitate to visit our Vcedump.com to find your solutions here.