You are the Scrum Master of the JKM Project and your Development Team has asked to change some rules about the duration of the Sprints. Which one of the following statements is a rule of Scrum that the team should follow when it comes to Sprint duration?
A. Multiple Scrum teams can have sprints of different duration in one project.You are the Scrum Master for the USB Project for your organization. The Development Team has completed three iterations and they want to know when Kim, the Product Owner, will release the completed increments into production. What's the best answer?
A. Increments are released to production when the customer requires the increments.A CEO asks the Development Team to add a new item to the Sprint. What should the Development Team do in response?
A. Refer it to the Product OwnerYou are the Scrum Master for a new project. This project will have 80 developers contributing to the product. As a Scrum Master, how would you divide a group of 80 people into multiple Development Teams?
A. Create ten teams of eight people per team.Suppose you are a Scrum Master on a project to design a metro rail system for a city. It has been brought to your attention that the Product Owner wants to change the Acceptance Criteria for one of the User Stories committed to for the current Sprint because the customer has changed a critical business requirement. Which one of the following statements presents the best solution for such a situation?
A. You should direct the Scrum team to stop working on the current Sprint Backlog, and to start working on the latest business requirements.The Scrum Team along with the Scrum Master adopted the Fist of Five technique to arrive at accurate estimations for the prioritized User Stories. The results of the vote of each team member are as follows: three members: 2 fingers; four members: 3 fingers; and two members: 5 fingers. Which of the following options is in plurality?
A. I am not sure and would like to go with the group's consensus conclusion.During a Scrum of Scrums Meeting certain are answered. Which of the following are the answered?
A. What has my team been working on since the last meeting?A company that builds propellers for ships has incurred heavy losses while implementing the product at the end of the project. This is because a large number of customer requirements which changed during the project were not incorporated into the deliverables. The company could have avoided this situation if it had applied the Scrum Methodology, as it would have ensured that any change requested by the customer was included as part of the project, and that the team produced deliverables that were better suited to the final business environment. Which Scrum aspect is being emphasized here?
A. Value-based prioritizationAs a Scrum Master you should be familiar with all roles and responsibilities of a Scrum Project Which role can also be described as a Value Optimizer for the project?
A. Product OwnerKelly is the Scrum Master for her organization and she's meeting with her manager to discuss the skillsets required for the Development Team. Kelly tells her manager what fact about what the Development Team needs in every Scrum project?
A. The Development Team will need the skills and know-how to deliver a Done IncrementNowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Scrum exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your SCRUM-SMC exam preparations and Scrum certification application, do not hesitate to visit our Vcedump.com to find your solutions here.