Question 1 Single choice

What is one strategy for managing complex critical path challenges?

  1. A

    Adjust work between teams or split Features and Stories

  2. B

    Distribute work to other teams

  3. C

    Sequence work to eliminate same Iteration dependencies

  4. D

    Allocate work between teams based on forecasted capacity

Show answer and explanation

Correct answer: A

Explanation

One strategy for managing complex critical path challenges is to adjust work between teams or split Features and Stories. Complex critical path challenges are situations where the delivery of value depends on the completion of multiple interdependent tasks by different teams. These challenges can cause delays, bottlenecks, and inefficiencies in the value stream. To overcome these challenges, one option is to adjust work between teams or split Features and Stories, so that the dependencies are minimized or eliminated.
This can help improve the flow of work, reduce the risk of integration issues, and increase the flexibility and responsiveness of the teams.

References:
Accelerating Flow with SAFe - Scaled Agile Framework Managing Dependencies - Scaled Agile Framework

Question 2 Single choice

What makes value available when it's needed?

  1. A

    Release on Demand

  2. B

    DevOps

  3. C

    Continuous Deployment

  4. D

    Infrastructure

Show answer and explanation

Correct answer: A

Explanation

Release on Demand is the process that makes value available to customers when it's needed. It is the final aspect of the Continuous Delivery Pipeline, which represents the workflows, activities, and automation needed to guide new functionality from ideation to an on-demand release of value. Release on Demand allows the business to release the solution to the end users or customers in acontrolled or staggered manner, based on the market and business needs. Release on Demand enables the enterprise to respond quickly to customer feedback, optimize the timing and frequency of releases, and reduce the risk associated with each release.

References:
Continuous Delivery Pipeline - Scaled Agile Framework
Release on Demand - Scaled Agile Framework.
What is Release on Demand? | Definition and Overview

Question 3 Single choice

What is the primary purpose of PO Sync?

  1. A

    To assess progress of the PI and adjust scope and priority as needed

  2. B

    To build PI Objectives and improve alignment

  3. C

    To align with Coach Sync participants on the status of the PI

  4. D

    To conduct backlog refinement

Show answer and explanation

Correct answer: A

Explanation

The primary purpose of PO Sync is to assess progress of the Program Increment (PI) and adjust scope and priority as needed 12. PO Sync is a regular event that involves the Product Owners from all the Agile teams in an Agile Release Train (ART). In PO Sync, they share the status of their work, identify dependencies, risks, and impediments, and align on the product vision and roadmap. PO Sync helps to ensure that the ART delivers value to the customers and meets the PI objectives.

Some additional information that might be helpful for you are:

The other options (B, C, and D) are not the primary purpose of PO Sync, but rather purposes of other events or activities.

Building PI Objectives and improving alignment is the purpose of PI Planning, which is a two-day event that occurs at the beginning of each PI3. In PI Planning, all the members of the ART collaborate to define, prioritize, and plan the work for the next PI.

Aligning with Coach Sync participants on the status of the PI is the purpose of Scrum of Scrums (SoS), which is a regular event that involves the Scrum Masters from all the Agile teams in an ART. In SoS, they coordinate and synchronize the work of the teams, resolve cross-team impediments, and report the progress and risks to the RTE.

Conducting backlog refinement is an activity that occurs throughout the PI, where the Product Owner and the Development team review and update the Team Backlog to prepare for the upcoming Iterations.
Backlog refinement helps to ensure that the work items are clear, feasible, and valuable

Question 4 Single choice

Which is developed by teams and rolled up to the ART level during PI Planning?

  1. A

    Dependencies

  2. B

    Milestones

  3. C

    Objectives

  4. D

    Risks

Show answer and explanation

Correct answer: C

Explanation

Objectives are developed by teams and rolled up to the ART level during PI Planning. Objectives are a summary of the business and technical goals that the teams and the ART intend to achieve in the upcoming Program Increment (PI). During PI Planning, each team creates their own team PI objectives,
which are then presented and reviewed by the ART and the stakeholders. The aggregated team PI objectives form the ART PI objectives, which provide a common vision and alignment for the ART.

References:
PI Objectives - Scaled Agile Framework
PI Planning - Scaled Agile Framework

Question 5 Single choice

What is one responsibility of Product Management?

  1. A

    Managing and prioritizing the Team Backlog

  2. B

    Supporting the team in delivering value

  3. C

    Connecting with the Customer

  4. D

    Building the Solution

Show answer and explanation

Correct answer: C

Explanation

One of the key responsibilities of Product Management in SAFe is to connect with the customer and understand their needs, preferences, and feedback. Product Management is the voice of the customer for the Agile Release Train (ART) and represents their interests in defining and prioritizing the features and capabilities of the solution. Product Management also engages withthe customer throughout the product life cycle, conducting market research, validating assumptions, soliciting feedback, and ensuring customer satisfaction.

References:
Product Management - Scaled Agile Framework
The Role of Product Management in the Scaled Agile Framework (SAFe) - iZenBridge

Question 6 Single choice

What can increase the effectiveness of Backlog Refinement?

  1. A

    Include a few team members

  2. B

    Refine Stories during Iteration Planning

  3. C

    Schedule the event on a regular cadence

  4. D

    Have separate meetings with subject matter experts

Show answer and explanation

Correct answer: C

Explanation

One of the factors that can increase the effectiveness of Backlog Refinement is to schedule the event on a regular cadence. Backlog Refinement is the process of reviewing, updating, and prioritizing the backlog items to prepare them for future iterations or sprints. By scheduling the event on a regular cadence, such as once or twice per week, the team can ensure that the backlog is always accurate, relevant, and ready for planning. A regular cadence also helps the team to avoid cramming too much work into a single session, which can lead to lower quality and reduced collaboration.

References:
Team Backlog - Scaled Agile Framework
Backlog refinement - How I learned to love agile business analysis ...
Essential Checklist for Effective Backlog Refinement (and What To Avoid ...

Question 7 Single choice

What is one method for designing the end-to-end Customer experience?

  1. A

    Journey mapping

  2. B

    Whole-product thinking

  3. C

    Feature storming

  4. D

    Persona development

Show answer and explanation

Correct answer: A

Explanation

Journey mapping is one method for designing the end-to-end customer experience. It is a visual representation of the steps, emotions, and pain points that a customer goes through when interacting with a product or service. It helps to identify the customer needs, expectations, and goals, as well as the gaps and opportunities for improvement in the current experience. Journey mapping also helps to align the stakeholders on the customer perspective and prioritize the features and solutions that will deliver the most value and satisfaction

References:
The expanding role of design in creating an end-to-end customer experience
End to End Customer Experience: Know and Control its 3 Elements - HEFLO BPM
How Design thinking Can Shape end to end Customer Experience

Question 8 Single choice

In the first step of SAFe's Continuous Delivery Pipeline, Product Owners and Product Managers do what activity?

  1. A

    Ensure the Architecture team has sufficient capacity

  2. B

    Negotiate Supplier contracts

  3. C

    Prioritize the Team Backlog

  4. D

    Hypothesize what would create value for Customers

Show answer and explanation

Correct answer: D

Explanation

Hypothesizing what would create value for customers is the main activity of Product Owners and Product Managers in the first step of SAFe's Continuous Delivery Pipeline, which is Continuous Exploration (CE).
In CE, they use design thinking to understand the market problem or customer need and the solution required to meet that need. They start with a hypothesis of something that will provide value to customers, such as a new feature, capability, or enhancement. They then validate or invalidate their hypothesis through experimentation, feedback, and learning.

Some additional information that might be helpful for you are:

The other options (A, B, and C) are not the main activity of Product Owners and Product Managers in the first step of SAFe's Continuous Delivery Pipeline, but rather activities that may occur in other steps or roles.

Ensuring the Architecture team has sufficient capacity is an activity that may occur in the second step of SAFe's Continuous Delivery Pipeline, which is Continuous Integration (CI). In CI, the Architecture team works with the Development teams to ensure the technical quality and integrity of the solution.

Negotiating Supplier contracts is an activity that may occur in the fourth step of SAFe's Continuous Delivery Pipeline, which is Release on Demand. In Release on Demand, the Solution Management team works with the Suppliers to coordinate the release of the solution components that are provided by them.

Prioritizing the Team Backlog is an activity that occurs in the Program Increment (PI) Planning event, which is part of the Agile Product Delivery competency. In PI Planning, the Product Owner works with the Development team and other stakeholders to define, prioritize, and estimate the work items for the upcoming P.

Question 9 Single choice

What is one input to the Vision?

  1. A

    Customer feedback

  2. B

    Team topologies

  3. C

    Feature context

  4. D

    Portfolio Backlog

Show answer and explanation

Correct answer: A

Explanation

One input to the Vision is customer feedback. Customer feedback is the information and opinions that customers and stakeholders provide about the solution, its features, and its value proposition. Customer feedback helps to validate the assumptions, test the hypotheses, and measure the satisfaction of the solution. Customer feedback also helps to identify the needs, preferences, and expectations of the customers and stakeholders, which are essential for defining and communicating the Vision. The Vision is a description of the future state of the solution under development, and it reflects the problem(s) that the solution will solve and the benefits that it will deliver.

References:
Customer Feedback - Scaled Agile Framework
Continuous Exploration - Scaled Agile Framework
Solution Vision - Scaled Agile Framework
Vision - Scaled Agile Framework

Question 10 Single choice

Which Product Owner responsibility supports the team with value delivery?

  1. A

    Understanding market forces

  2. B

    Supporting the Architectural Runway

  3. C

    Testing benefit hypotheses

  4. D

    Fostering Built-in Quality

Show answer and explanation

Correct answer: D

Explanation

Fostering Built-in Quality is a Product Owner responsibility that supports the team with value delivery. Built-in Quality is one of the four core values of SAFe?and it means that every aspect of the solution is continuously verified for quality. The Product Owner fosters Built-in Quality in the following ways:

Collaborating with the Development team and other stakeholders to define clear and testable acceptance criteria for each work item.
Participating in team events such as Iteration Planning, Backlog Refinement, and Iteration Review to provide feedback and guidance on the quality of the work.
Reviewing and approving the work items that meet the Definition of Done and the acceptance criteria.
Encouraging the team to apply Agile testing practices such as Test-First, Test-Driven Development, and Behavior-Driven Development.
Supporting the team's continuous integration and continuous delivery practices to ensure fast and frequent feedback on the quality of the solution.

Some additional information that might be helpful for you are: The other options (A, B, and C) are not Product Owner responsibilities that support the team with value delivery, but rather responsibilities that belong to other roles or activities.
Understanding market forces is a responsibility of Product Management, who is accountable for the market and business aspects of the solution.
Supporting the Architectural Runway is a responsibility of System Architects/Engineers, who provide technical guidance and enablement to the teams.
Testing benefit hypotheses is an activity that occurs in the Continuous Exploration step of the Continuous Delivery Pipeline, where Product Owners and Product Managers collaborate to validate their assumptions about the customer and the solution.