  • Question 121:

    Which two statements are the most accurate in regards to scaling Scrum for large projects requiring multiple Scrum Teams? (Choose two.)

    A. A person focusing on the Sprint Backlog of a single Scrum Team is often more productive than that same person working on multiple Scrum Teams at the same time.

    B. A well-structured Product Backlog can minimize and often eliminate Development Team members working on multiple Scrum Teams during a Sprint.

    C. Team members must work full time on a single Scrum Team.

    D. Customizing the core Scrum framework is necessary to be successful with Scrum at large scale.

  • Question 122:

    Which two behaviors would reflect Servant Leadership in a Scrum Master? (Choose two.)

    A. Facilitating Scrum Events as requested or needed.

    B. Coaching the Development Team, the Product Owner and the organization on how to work empirically.

    C. Staying away from internal Development Team interactions, maximizing their autonomy and freedom.

    D. Resolving every impediment for the Development Team.

  • Question 123:

    A Scrum Team must have a Product Owner and Scrum Master.

    A. False. A Scrum Master is only necessary when requested or needed.

    B. True. Each must be a full-time member on the Scrum Team.

    C. True. Their participation and availability will impact the outcomes produced by the Scrum Team.

    D. False. If a Product Owner is unavailable, he/she can be replaced by a Business Analyst.

  • Question 124:

    A new member has just joined an existing Development Team that has been together for several Sprints. During the Sprint, the individual has been trying to share his ideas and viewpoints but is continuously ignored by the rest of the Development Team.

    Which three Scrum Values has the Development Team been neglecting? (Choose three.)

    A. Commitment

    B. Respect

    C. Transparency

    D. Focus

    E. Openness

    F. Courage

  • Question 125:

    Scrum has a role called "Project Manager."

    A. True

    B. False

  • Question 126:

    A Scrum Team has been working on the same product for twelve Sprints. What would likely be the immediate impact on the original Scrum Team if two new Scrum Teams are to be added the same product?

    A. Its productivity is likely to decrease.

    B. Its productivity is likely to increase.

    C. Its productivity is likely to stay the same.

  • Question 127:

    What would be the main benefits of self-organization?

    A. Increased rule compliance, self-accountability, commitment.

    B. Increased rule compliance, self-accountability, output.

    C. Increased capacity, accuracy of estimates, output.

    D. Increased creativity, self-accountability, commitment.

  • Question 128:

    Select the correct Scrum Team roles defined in Scrum.

    A. Development Team, Scrum Master, Product Owner

    B. Engineers, Business Analyst, Product Owner

    C. Stakeholders, Scrum Master, Project Manager, Product Owner

    D. Product Manager, Business Analyst, Development Team, Stakeholders

  • Question 129:

    At the eighth Sprint Review, the stakeholders are upset that the product being built is not what they expected and will incur additional costs that was not planned for. What may have led to this?

    A. The Scrum Master has not been reporting on the progress of the Scrum Team. The Product Owner has not been managing the Development Team's tasks effectively. The Development Team has not been improving their velocity.

    B. The Scrum Master has not ensured that the project is transparent. The Product Owner has not made the stakeholders aware of the progress of the project. The stakeholders have not been attending the Sprint Reviews.

    C. The Scrum Master has not been attending the Daily Standup. The Product Owner has not been using the Gantt chart correctly. The Stakeholders has not been invited to the Sprint Retrospectives.

  • Question 130:

    When technical debt occurs, the system will become more unstable as development progresses and code is added resulting in future work being slowed down.

    A. True

    B. False

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Scrum exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PSM-II exam preparations and Scrum certification application, do not hesitate to visit our Vcedump.com to find your solutions here.