Exam Details

  • Exam Code
    :PSM-I
  • Exam Name
    :Professional Scrum Master I
  • Certification
    :Professional Scrum Master
  • Vendor
    :Scrum
  • Total Questions
    :267 Q&As
  • Last Updated
    :May 12, 2024

Scrum Professional Scrum Master PSM-I Questions & Answers

  • Question 221:

    Who must attend the Daily Scrum?

    A. The Scrum Master and Product Owner.

    B. The Development Team.

    C. The Development Team and Product Owner.

    D. The Scrum Team.

    E. The Development Team and Scrum Master.

  • Question 222:

    Which of the following is required by Scrum?

    A. Sprint Retrospective.

    B. Members must be stand up at the Daily Scrum.

    C. Sprint Burndown Chart.

    D. Release planning.

    E. All of the above.

  • Question 223:

    What is the purpose of a Sprint Review?

    A. To take time to judge the validity of the project.

    B. To inspect the product Increment with the stakeholders and collect feedback on next steps.

    C. To review the Scrum Team's activities and processes during the Sprint.

    D. To build team sprint.

  • Question 224:

    Which answer best describes the topics covered in Sprint Planning?

    A. What to do and who will do it.

    B. How conditions have changed and how the Product Backlog should evolve.

    C. What can be done and how to do it.

    D. What went wrong in the last Sprint and what to do differently this Sprint.

    E. Who is on the team and what team member roles will be.

  • Question 225:

    In the Sprint Planning meeting, the Product Owner and the Development Team were unable to reach a clear understanding about the highest order Product Backlog items. Because of this, the Development Team couldn't figure out how many Product Backlog items it could forecast for the upcoming Sprint. They were able to agree on a Sprint Goal, however.

    Which of the following two actions should the Scrum Master support? (Choose two.)

    A. Cancel the Sprint. Send the entire team to an advanced Scrum training and then start a new Sprint.

    B. Forecast the most likely Product Backlog items to meet the goal and create a Sprint Backlog based on a likely initial design and plan. Once the time-box for the Sprint Planning meeting is over, start the Sprint and continue to analyze, decompose, and create additional functionality during the Sprint.

    C. Continue the Sprint Planning meeting past its time-box until an adequate number of Product Backlog items are well enough understood for the Development Team to make a complete forecast. Then start the Sprint.

    D. Discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur.

    E. Ask everyone to take as much time as needed to analyze the Product Backlog first, and then reconvene another Sprint Planning meeting.

  • Question 226:

    How much time is required after a Sprint to prepare for the next Sprint?

    A. The break between Sprints is time-boxed to 1 week for 30 day Sprints, and usually less for shorter sprints.

    B. Enough time for the requirements for the next Sprint to be determined and documented.

    C. Enough time for the Development team to finish the testing from the last Sprint.

    D. None. A new Sprint starts immediately following the end of the previous Sprint.

    E. All of the above are allowed depending on the situation.

  • Question 227:

    What are two good ways for the Development Team to make non-functional requirements visible? (Choose two.)

    A. Put them on a separate list on the Scrum board, available for all to see.

    B. Add them to the Product Backlog and keep the Product Owner posted on the expected effort.

    C. Run the integration and regression tests before the end of the Sprint, and capture the open work for the Sprint Backlog of the next Sprint.

    D. Add them to the definition of "Done" so the work is taken care of every Sprint.

  • Question 228:

    Scrum has a role called "Project Manager".

    A. True

    B. False

  • Question 229:

    When is a Sprint over?

    A. When the Product Owner says it is done.

    B. When all Product Backlog items meet their definition of "Done".

    C. When all the tasks are completed.

    D. When the time-box expires.

  • Question 230:

    How should a Development Team deal with non-functional requirements?

    A. Ensure every Increment meets them.

    B. Make sure the release department understands these requirements, but it is not the Development Team's responsibility.

    C. Handle them during the Integration Sprint preceding the Release Sprint.

    D. Assign them to the lead developers on the team.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Scrum exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PSM-I exam preparations and Scrum certification application, do not hesitate to visit our Vcedump.com to find your solutions here.