  • Question 161:

    What is the time-box for the Sprint Review?

    A. As long as needed.

    B. 2 hours for a monthly Sprint.

    C. 4 hours for a monthly Sprint.

    D. 4 hours and longer as needed.

    E. 1 day

  • Question 162:

    A product Increment must be released to production at the end of each Sprint.

    A. True

    B. False

  • Question 163:

    If burndown charts are used to visualize progress, what do they track?

    A. Accumulated cost.

    B. Individual worker productivity.

    C. Work remaining across time.

    D. Accumulated business value delivered to the customer.

  • Question 164:

    A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which three techniques would be most helpful in this situation? (Choose three.)

    A. Consulting with the Development Team.

    B. Prioritizing the list and working on them in order.

    C. Arranging a triage meeting with all project managers.

    D. Alerting management to the impediments and their impact.

  • Question 165:

    Which Scrum Value is affected by a lack of trust in the Scrum Team?

    A. Focus

    B. Respect

    C. Openness

    D. Courage

    E. Commitment

    F. All of the above

  • Question 166:

    What is the time-box for the Sprint Planning meeting?

    A. 4 Hours for a monthly Sprint.

    B. 8 Hours for a monthly Sprint.

    C. Monthly.

    D. Whenever it is done.

  • Question 167:

    Which two ways of creating Development Teams are consistent with Scrum's values? (Choose two.)

    A. Existing teams propose how they would like to go about organizing into the new structure.

    B. Managers personally re-assign current subordinates to new teams.

    C. Managers collaborate to assign individuals to specific teams.

    D. Bring all the developers together and let them self-organize into Development Teams.

    E. The Chief Product Owner determines the new team structures and assignments.

  • Question 168:

    A Scrum Master is essentially the same thing as a traditional PM (Project Manager).

    A. True

    B. False

  • Question 169:

    What is a Development Team responsible for? (Choose two.)

    A. Resolving internal team conflicts.

    B. Reporting productivity.

    C. Selecting the Product Owner.

    D. Organizing the work required to meet the Sprint Goal.

  • Question 170:

    A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give?

    A. Product Backlog items must be estimated in story points.

    B. Estimates are made by the Development Team.

    C. Estimates must be in relative units.

    D. Scrum forbids estimating.

    E. Estimates are made by the Product Owner, but are best checked with the Development Team.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Scrum exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PSM-I exam preparations and Scrum certification application, do not hesitate to visit our Vcedump.com to find your solutions here.