Which is one of the four tasks of PRINCE2s recommended approach to defining and analyzing the products?
A. To write the project product description
B. To create the project plan
C. To prepare estimates
D. To produce a product status account
Which role must only be carried out by one individual?
A. Project assurance
B. Executive
C. User representative
D. Supplier representative
Which describes a purpose of the “starting up a project” process?
A. To prevent poorly conceived projects from progressing to initiation
B. To plan delivery of the project's products before committing to significant spend
C. To approve the customer's quality expectations and defined acceptance criteria
D. To identify how the project's products will be controlled and protected
Which is a benefit gained from applying the “defined roles and responsibilities” principle?
A. Management control is provided by review and decision points at defined intervals
B. Management time is saved by setting tolerances for each management level
C. Recommendations made by members of other project teams are considered
D. Clear accountabilities are established for all members of the project team
Which statement about applying the “tailor to suit the project” principle is CORRECT?
A. PRINCE2 can be tailored to be used with any type of project
B. A technically complex project should NOT tailor PRINCE2
C. The tailoring of PRINCE2 is MOST appropriate for agile projects
D. A project which is part of a program should NOT tailor PRINCE2
Which statement about stakeholder interests is CORRECT?
A. Supplier interest begins as soon as the project starts to deliver products, and ends at project closure
B. Business interest ensures that the project satisfies the requirements of those who will use the outputs
C. Business, user and supplier interests have decision making authority in the project management team
D. The project board can operate without supplier interest representation during the initiation stage
Identify the missing words in the following sentence.
The quality theme applies the ”[ ? ]” principle by ensuring that there is a common understanding of what the project will create.
A. continued business justification
B. focus on products
C. defined roles and responsibilities
D. manage by stages
Identify the missing word in the following sentence.
The PRINCE2 [ ? ] provide the guiding obligations and good practices, which all have to be applied in order to ensure that the project is being managed using PRINCE2.
A. themes
B. principles
C. processes
D. techniques
Which statement about the role of the project manager is CORRECT?
A. The project manager must not delegate any responsibilities
B. The project manager must not take on an additional role
C. The project manager role must not be shared
D. The project manager must not come from the supplier
Which is an objective of the “closing a project” process?
A. To review and approve the plan for project closure
B. To review the performance of the project against its baseline
C. To perform any post-project reviews
D. To create a benefits management approach
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.